Nigeria road upgrade funding increased

An increase in the budget has been made for the Ikot Ekpene-Aba-Owerri road widening project in South East Nigeria. This route is to be improved and widened so that it has two lanes in either direction, rather than just one at present. The route is a busy one as it provides a central link between the busy commercial city of Onitsha, Imo State capital Owerri and the state capital of Akwa Ibom State, Uyo. This route also connects Onitsha to Calabar, State capital of Cross River State, which lies close the bor
April 17, 2019 Read time: 2 mins
An increase in the budget has been made for the Ikot Ekpene-Aba-Owerri road widening project in South East Nigeria. This route is to be improved and widened so that it has two lanes in either direction, rather than just one at present. The route is a busy one as it provides a central link between the busy commercial city of Onitsha, Imo State capital Owerri and the state capital of Akwa Ibom State, Uyo. This route also connects Onitsha to Calabar, State capital of Cross River State, which lies close the border with Cameroon.


However the route has declined in standard due to lack of maintenance over many years, with the rainy season posing a particular challenge to transport. The Nigerian Federal Government initially set a budget of US$10.4 million for the project in 2021. However this has now been increased to $17 million. The work is being carried out by the Egyptian firm, Arab Contractors.

Related Content

  • New Nigerian road and bridge transport connection
    March 3, 2020
    A new road and bridge transport connection is proposed for South East Nigeria.
  • South Eastern Nigerian road project stalls
    July 24, 2019
    Construction work on the upgrade of the road connecting Calabar with Itu and Ikot Ekpene in South East Nigeria has once again ground to a halt. The contractor carrying out the work, Julius Berger, has transferred personnel and equipment to other projects. This action has been taken due to a delay in payments for the work to the contractor. The road is now in extremely poor condition, which is a key problem for transport between Cross River State and Akwa Ibom State. Much of the road is now said to be virt
  • Highway construction to be completed for South East Nigeria
    June 11, 2018
    Further financing will be required to complete construction work for Nigeria’s vital East-West highway project. Work is being carried out on sections of the highway between Warri and Port Harcourt and from Eket to Ikot Akan and Atan Ikpe. The former stretch is being handled by Setraco Nigeria, while the latter is being handled by Reynolds Construction Company. However a further US$277.4 million will be required to fund the work, which involves widening the highway so that it features two lanes in either dir
  • Nigerian highway concessions being offered
    September 14, 2021
    More Nigerian highway concessions are being offered.