Mombasa-Tanga link faces delays over design changes

Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga. The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway. However, the African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.
April 10, 2018 Read time: 3 mins
Kenya has blamed design changes for delaying the start of work on a road linking the port of Mombasa to the Tansanian port of Tanga.


The change to the key road’s design is from a single to dual carriageway along a section of the 445km transnational highway.

However, the 1586 African Development Bank (AfDB), the principal financier of the project, said the Kenyan government itself was slow in completing preliminary studies, such as road designs, in order to start construction.

The road from Malindi on the Kenyan coast to Bagamoyo - formerly a key trading port in north-eastern Tanzania during colonial times - will cost around US$751 million, according to the Kenya-based newspaper Business Daily Africa. AfDB will fund about 70% of the project, with the two countries covering 30% of the total cost in their respective territories.

Work on the mega project that is expected to take 36 months but the start of construction has been delayed since 2016. It was expected to start this year, but a start is now not likely until next year.

Kenya’s transport and infrastructure secretary James Macharia said the new designs will ensure that the stretch from Mtwapa to Nyali in Mombasa - including the Mtwapa Bridge - is expanded from a single to dual carriage as in the previous designs.

“We had to change the designs to make sure we do not have a bottleneck at Nyali-Mtwapa area because traffic there is a very big problem,” Macharia reportedly said. “Designs for the [Mtwapa] bridge can be complex and need time to ensure it is done properly.”

Kenya started the tendering process for contractors to do feasibility studies and environmental impact assessments last month; Tanzania has already completed this aspect of the project inside their borders.

“Tanzania is moving faster than Kenya, but since it is a multinational project, the two countries have to come together,” said Gabriel Negatu, the AfDB director-general for business development and delivery in East Africa. “Once the detailed designs are done, we will proceed either this year or next.”

The 250km Kenyan section of the transnational highway starts in Malindi and runs  through Mombasa and on to Lunga Lunga at the border with Tanzania. Most of the project is rehabilitation of the existing road.

It will then cross into Tanzania through Tanga port and stretch 175km to Bagamoyo, a world heritage town as designated by the United Nations Educational, Scientific and Cultural Organisation (1384 UNESCO).

This will be the third transnational road project by the two countries. Previous projects included the are the $260 million Arusha-Namanga-Athi River Road.

For more information on companies in this article

Related Content

  • Kenya highway project tendering opens
    September 26, 2016
    The tender process is opening for the Nairobi-Mombasa highway project in Kenya. The plan calls for the existing route to be widened from two lanes at present to six lanes, with three in either direction. This will help boost capacity on the busy route between capital Nairobi and the main port of Mombasa, aiding trade and transport for Kenya as well as its neighbours. The Kenyan Government intends for the highway project to be carried out under the Public Private Partnership (PPP) model. Should all go to pla
  • Bangladesh, China seal $705 million deal for Karnaphuli River tunnel
    July 2, 2015
    Bangladesh has formally signed a US$705 million deal with China Communication Construction to build a multi-lane road tunnel underneath the Karnaphuli River in Chittagong. Road Transport and Bridges secretary Man Siddique along with the government’s Road Transport and Bridges minister Obaidul Quader signed the contract with Liu Qitao, chairman of China Communication Construction. The signing took place in Beijing, according to a report in the Bangladesh newspaper The Independent.
  • Volvo CE’s electric quarry operation commences trials
    August 29, 2018
    Volvo CE is commencing operations of its low emission quarrying operation in Sweden. The facility has a strong focus on electric machines, with diesel-electric hybrid equipment also being used. According to the firm, this is a world first for a quarry facility that can be run almost 'emission-free'. Volvo CE and its customer Skanska have now commenced testing the viability of the Electric Site concept at Skanska’s Vikan Kross quarry, located near Gothenburg in Sweden. The production system at the site
  • PPRS: smarter, more sophisticated asset management is needed
    March 27, 2018
    Highway organisations around the world will need ever-more sophisticated frameworks to ensure their asset management is up-to-date and fit-for-purpose. Jacques Tavernier, chairman of PPRS Nice 2018, and Claude van Rooten, president of PIARC, the World Road Association emphasised the point at at this week’s Pavement Preservations and Recycling Summit. A nation’s roads are its first and most important “main asset … essential for a country’s economic, social and environmental development”, said van Roote