Koridori Srbije said it is suffering delays to Corridor 10 work

Koridori Srbije, the contractor building the eastern section of the Corridor 10 motorway between Nis and the Bulgarian border, said completion will be delayed. The newspaper Vecernje Novosti reported that Koridori Srbije said works on the Prosek-Bancarevo section, Crvena Reka-Ciflik, Pirot East-Dimitrovgrad and the Bancarevo tunnel should be finished by the end of the year. Construction on the Dimitrovgrad ringroad are due to be completed in March.
October 18, 2016 Read time: 1 min
3235 Koridori Srbije, the contractor building the eastern section of the Corridor 10 motorway between Nis and the Bulgarian border, said completion will be delayed.

The newspaper Vecernje Novosti reported that Koridori Srbije said works on the Prosek-Bancarevo section, Crvena Reka-Ciflik, Pirot East-Dimitrovgrad and the Bancarevo tunnel should be finished by the end of the year.

Construction on the Dimitrovgrad ringroad are due to be completed in March.

For more information on companies in this article

Related Content

  • Serbia starts in-depth talks with the Chinese for Corridor 11 work
    May 7, 2015
    Serbia has entered into “in depth” negotiations with two Chinese companies for concession contracts along the Corridor 11 motorway between Belgrade and the Montenegrin border. Shandong High Speed Group and the China Road and Bridge Corporation (CRBC) are the two Chinese companies that have passed the pre-qualification process. The project value has not been mentioned. Serbian vice president Zorana Mihajlovic said that the Chinese have requested guarantees for transport and Serbia is considering this a
  • EBRD mulls loan for Macedonian Corridor 8 work
    July 13, 2021
    The €110million (US$ 130.5 million) load would help construct a 10.7km section, including a tunnel, between Bukojcani and Kicevo.
  • Progress on Serbia’s Zezeljev bridge replacement is slow
    August 30, 2017
    Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp
  • Progress on Serbia’s Zezeljev bridge replacement is slow
    August 30, 2017
    Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp