Key highway sections to be completed in Serbia in 2017

A series of major highway sections in Serbia should be completed during 2017, including work to two stretches of the key Corridor 10 project. In all, some 122km of highways are expected to be opened to traffic in Serbia during 2017. Greek contractor Actor is building an 18km stretch of Corridor 10 that runs from Surcin to Obrenovac part. This firm is also building a 19.5km section of Corridor 10 from the Ostruznica Bridge that spans the Sava River to Bubanj Potok, and a further 10km section leading to Buban
January 16, 2017 Read time: 2 mins
A series of major highway sections in Serbia should be completed during 2017, including work to two stretches of the key Corridor 10 project. In all, some 122km of highways are expected to be opened to traffic in Serbia during 2017.

Greek contractor Actor is building an 18km stretch of Corridor 10 that runs from Surcin to Obrenovac part. This firm is also building a 19.5km section of Corridor 10 from the Ostruznica Bridge that spans the Sava River to Bubanj Potok, and a further 10km section leading to Bubanj Potok. The Srpska Kuca to Levosoje stretch of highway meanwhile is being built by a group of companies.

Costing €297.4 million, the Belgrade-South Adriatic highway project is being carried out by Chinese contractor Shandong High Speed Group. Funding has been delivered by China's Exim Bank. This is a complex highway project which includes the construction of 12 tunnel stretches as well as 234 bridges.

Related Content

  • Serbia: end in sight for finishing southern part of Corridor 10
    August 26, 2016
    Serbia’s minister of construction and infrastructure, Zorana Mihajlovic, said that the southern part of the Corridor 10 motorway is expected to be completed by the end of 2017. Speaking to the Beta news agency, she also said that work on the Corridor 11 motorway, on the Ub-Lajkovac section, is being carried out in cooperation with Chinese partner company Shang Dong. The government has also signed an agreement for construction of the Surcin-Obrenovac part of the Corridor 11. Ongoing talks between Serbi
  • Progress on Serbia’s Zezeljev bridge replacement is slow
    August 30, 2017
    Construction of the Zezeljev rail and road bridge across the Danube River is facing further delays, according to the Serbian government. Work on the 470m-long new bridge was supposed to be finished by this month. But national elections and changes of government have hampered progress, Serbian media have reported. The original bridge was completed in 1961 as a single-track railway line and separate roadway between the cities of Novi Sad and Petrovaradin. NATO attacked the structure five times during its camp
  • Six years for Belgrade-Novi Sad highway
    September 17, 2024
    Total cost of the 100-km project in Serbia is estimated at €1.6 billion and will be completed by the Chinese company Shandong Hi-Speed Group.
  • Progress is being made with Serbia’s Corridor 11 highway project
    October 8, 2012
    Work is underway in Serbia for the Corridor 11 highway project and a number of local firms are now carrying out construction work on the Corridor 11 section from Ub to Lajkovac. Meanwhile Azvirt from Azerbaijan is preparing the Ljig to Preljina stretch of the highway, with the €300 million work being financed by Azerbaijan. The Serbian Government is asking China’s Exim Bank for a long term loan of €850 million, of which €300 million would be for the Corridor 11 project and €550 million would be for the Mora