Ferry operators sink the financing plan for Fehmarn Belt link

The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules. The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure. Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for tr
December 17, 2018 Read time: 3 mins
Fehmarn Belt financing: up in the air for undersea tunnel

The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules.

The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure.

Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for transportation.

Ferry operators Scandlines and Stena Line which provide services between Europe and the Scandinavian peninsula, argued in the European Court that the grant level to be given to whichever company operating the toll structure is based on unrealistically high traffic volume predictions.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Ferries connects the islands in the region. Completion of the €8.7 billion project has been set for 2028. However, even before the European Court ruling, the project’s approval process had been bogged down over environmental issues, especially within the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

“We are satisfied with the ruling of the Court of Justice of the European Union. (…) Scandlines is not against a Fehmarn connection established with state aid. State aid may be necessary when completing such large-scale projects,” said Søren Poulsgaard Jensen, chief executive of Scandlines.

“However, we do expect correct procedure, which entails transparency and fair competition. The aid must therefore be accurately and realistically defined, and it must be based on consistent assumptions and safeguarded against abuse. It is decisive for us that the tunnel cannot use the state finances as its sees fit to impose taxpayer-financed price pressure when traffic volumes do not live up to the optimistic prognoses and the ferries appear competitive.”
 
The arguments are in line with Stena Line’s appeal which questioned the necessity of the aid, the duration of the aid and the undue distortion to the market by allowing the Fehmarn fixed link to dramatically reduce prices.

“In this case State aid has been granted illegally. That’s why we welcome the decision from the court to annul the aid granted by the Commission for the construction of the Fehmarn Belt connection,” said Claes Berglund, director public affairs and sustainability for Stena.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with 4782 Femern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

8721 COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps & portals). Meanwhile, 3392 SWECO is handling the design for the dredging and reclamation work.
 
A second framework contract, for technical support services to Femern, is being carried out by ÅF-Hansen & Henneberg.

For more information on companies in this article

Related Content

  • Poland-Germany tunnel project planned
    August 17, 2018
    A new road tunnel is planned to connect Poland’s Wollin Island with Usedom Island in Germany. The project is expected to cost €225 million. The project was originally intended to be built by an Italian contractor, however an Austrian firm now looks likely to build the link. The tunnel plans call for a 1.4km link to be constructed using a TBM. The tunnel would replace the ferry service operating at present, improving transport connections for the northern Polish city of Swinoujscie.
  • Carry on Movin’ On - Michelin’s mobility event
    October 15, 2018
    Many of the great and the good in the global mobility sector gathered at this year’s Movin’ On event in Montreal. Measured regulation of technologies and safety issues were major themes, reports David Arminas Autonomous vehicles, platooning, smart intersections and safety – these were the talking points over two and half days of the Movin’ On event in Montreal. Everyone in the mobility sector is at the same point, trying to see what mobility will look like in the future. Apparent at the event was just
  • Sandvik’s DT1131i jumbo and iSURE software in Iceland and Norway
    August 14, 2019
    Sandvik’s DT1131i three-boom, electro-hydraulic jumbo, iSURE tunnel management software and the latest drill bit hardware were recently put to the test in Iceland and Norway* Czech contractor Metrostav recently achieved 105m of tunnel excavation in a record-breaking six days. But it will be consistent performance and progress that will see Iceland’s Dyrafjordurgong Tunnel in the remote Westfjords region open on time and on budget. The 5.3km Dyrafjordurgong Tunnel is costing around €69 million and due
  • Bridges and roads part of Myanmar’s New Yangon development
    April 6, 2018
    At least two bridges and dozens of kilometres of roads are part of phase one of an ambitious Myanmar plan to build a new city. Other infrastructure projects are an industrial zone, a power plant and water and sewage treatment plants, according to the newly created overseeing body, New Yangon Development Corporation - NYDC. The new city will cover around 30,000 acres on the west side of the Yangon River, including land in Kyimyindaing, Seikgyikanaungto and Twante townships. Much of the work to create the