Ferry operators sink the financing plan for Fehmarn Belt link

The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules. The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure. Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for tr
December 17, 2018 Read time: 3 mins
Fehmarn Belt financing: up in the air for undersea tunnel

The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules.

The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure.

Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for transportation.

Ferry operators Scandlines and Stena Line which provide services between Europe and the Scandinavian peninsula, argued in the European Court that the grant level to be given to whichever company operating the toll structure is based on unrealistically high traffic volume predictions.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Ferries connects the islands in the region. Completion of the €8.7 billion project has been set for 2028. However, even before the European Court ruling, the project’s approval process had been bogged down over environmental issues, especially within the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

“We are satisfied with the ruling of the Court of Justice of the European Union. (…) Scandlines is not against a Fehmarn connection established with state aid. State aid may be necessary when completing such large-scale projects,” said Søren Poulsgaard Jensen, chief executive of Scandlines.

“However, we do expect correct procedure, which entails transparency and fair competition. The aid must therefore be accurately and realistically defined, and it must be based on consistent assumptions and safeguarded against abuse. It is decisive for us that the tunnel cannot use the state finances as its sees fit to impose taxpayer-financed price pressure when traffic volumes do not live up to the optimistic prognoses and the ferries appear competitive.”
 
The arguments are in line with Stena Line’s appeal which questioned the necessity of the aid, the duration of the aid and the undue distortion to the market by allowing the Fehmarn fixed link to dramatically reduce prices.

“In this case State aid has been granted illegally. That’s why we welcome the decision from the court to annul the aid granted by the Commission for the construction of the Fehmarn Belt connection,” said Claes Berglund, director public affairs and sustainability for Stena.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with 4782 Femern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

8721 COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps & portals). Meanwhile, 3392 SWECO is handling the design for the dredging and reclamation work.
 
A second framework contract, for technical support services to Femern, is being carried out by ÅF-Hansen & Henneberg.

For more information on companies in this article

Related Content

  • Denmark: Fehmarn Tunnel contracts awarded to consortium
    June 3, 2016
    The Danish government has awarded €4.4 billion worth of contracts for the Fehmarn Tunnel that will link Germany and Denmark, according to Germany’s Frankfurter Allgemeine Zeitung newspaper. An international consortium that includes German Wayss und Freytag Ingenieurbau, Max Bögl Stiftung and Netherlands-based BAM picked up the work. Contracts include the excavation and construction of underground tunnels, manufacture of internal tunnel elements and the entry and exit ramps. Work is expected to star
  • Louis Berger wins key India bridge deal
    January 10, 2018
    Louis Berger has been awarded the management contract for the Versova-Bandra Sea Link project in India. The US$17 million project management services deal was awarded to the firm by the Maharashtra State Road Development Corporation (MSRDC). The construction of the Versova-Bandra Sea Link (VBSL) is estimated to cost some $1 billion and will take 54 months to complete. “We are honored to play a major role in one of the largest infrastructure projects — not just in Mumbai, but in India,” said Kshitish
  • Hamburg highway expansion programme
    May 20, 2015
    A €1.6 billion project is in hand in Germany to widen the A7 Autobahn between Bordesholm and Hamburg's tunnel Elbtunnel. Funding for the project is being provided jointly by the German Government, the city of Hamburg, the province of Schleswig-Holstein and the German engineering firm Deutsche Einheit Fernstraßenplanungs- und -bau (DEGES). The work should be complete by 2018. The project involves increasing the number of traffic lanes in the Schleswig-Holstein section from four to six and in Hamburg from six
  • Polish tunnel project being planned
    January 21, 2019
    Construction work on the planned tunnel for the Polish islands of Uznam and Wolin will commence in 2021. The islands lie on Poland’s Baltic Coast and this €184 million tunnel project is intended to improve transport connections in the area. The ferries used at present are ageing and are no longer able to cope adequately with the number of vehicles using the crossing. Up to 11,000 vehicles/day make the crossing during peak summer months, with around 2 million vehicles/year making the trip by ferry at present