Ferry operators sink the financing plan for Fehmarn Belt link

The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules. The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure. Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for tr
December 17, 2018 Read time: 3 mins
Fehmarn Belt financing: up in the air for undersea tunnel

The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules.

The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure.

Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for transportation.

Ferry operators Scandlines and Stena Line which provide services between Europe and the Scandinavian peninsula, argued in the European Court that the grant level to be given to whichever company operating the toll structure is based on unrealistically high traffic volume predictions.

The Fehmarn Belt is a strait between the German island of Fehmarn and the Danish island of Lolland. Ferries connects the islands in the region. Completion of the €8.7 billion project has been set for 2028. However, even before the European Court ruling, the project’s approval process had been bogged down over environmental issues, especially within the German state of Schleswig-Holstein in which the southern end of 18km immersed tunnel will surface.

“We are satisfied with the ruling of the Court of Justice of the European Union. (…) Scandlines is not against a Fehmarn connection established with state aid. State aid may be necessary when completing such large-scale projects,” said Søren Poulsgaard Jensen, chief executive of Scandlines.

“However, we do expect correct procedure, which entails transparency and fair competition. The aid must therefore be accurately and realistically defined, and it must be based on consistent assumptions and safeguarded against abuse. It is decisive for us that the tunnel cannot use the state finances as its sees fit to impose taxpayer-financed price pressure when traffic volumes do not live up to the optimistic prognoses and the ferries appear competitive.”
 
The arguments are in line with Stena Line’s appeal which questioned the necessity of the aid, the duration of the aid and the undue distortion to the market by allowing the Fehmarn fixed link to dramatically reduce prices.

“In this case State aid has been granted illegally. That’s why we welcome the decision from the court to annul the aid granted by the Commission for the construction of the Fehmarn Belt connection,” said Claes Berglund, director public affairs and sustainability for Stena.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with 4782 Femern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

8721 COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps & portals). Meanwhile, 3392 SWECO is handling the design for the dredging and reclamation work.
 
A second framework contract, for technical support services to Femern, is being carried out by ÅF-Hansen & Henneberg.

For more information on companies in this article

Related Content

  • Highways England to trial different speeds through road works
    August 6, 2018
    Highways England is trialling different speed limits through roadworks during different times in order to respond to drivers’ feedback. Highways England, the government-owned company responsible for modernising, maintaining and operating England’s motorways and major A roads, said it is acting on drivers’ frustration with roadworks. Speed through motorway roadworks could be increased depending on what day of the week they are travelling. The decision follows earlier trials to increase the speed l
  • Land acquisition delays the start of Bratislava's orbital road
    September 25, 2017
    Land acquisition issues have stalled the start of construction of Bratislava’s orbital road by up to eight months. Work could begin this autumn, according to a report by the Slovak Spectator, because the government is working on laws that would allow construction before all land is acquired.
  • Indra Sistemas joins European Commission’s study Harmony
    December 19, 2017
    Spanish global IT business Indra Sistemas is to join Harmony, a pan-European multimodal transport connectivity study. Harmony aims to develop technologies for integrating real-time data from different transport users and operators to improve multimodal information services. Indra will be focussed on a pilot project in Madrid, developed with the Polytechnic University of Madrid. Indra is working with research groups G@TV and TranSYT from the Polytechnic University of Madrid along with support from Grupo
  • West Africa’s biggest bitumen plant
    September 19, 2019
    July saw the ceremonial sod cutting for a project to build West Africa’s biggest bitumen plant: a joint venture between Ghana’s oil company GOIL and Societe Multinationale de Bitumes (SMB) of the Ivory Coast. The project, which will cost around US$35 million according to GOIL, is in Tema Ghana. With a capacity of 8,000tonnes, it will produce AC10 and AC20 bitumen and polymer modified bitumen (PMB). Speaking at the ceremony, Ghana’s minister of energy John Peter Amewu said: “Due to the success of the PMB