Delays plague Slovakia’s D1 motorway work

Slovakia is reporting delays to works on the D1 motor, the country’s major east-west corridor and part of several pan-European routes, including the E50. The planned 2020 completion of the D1 motorway linking Bratislava - Kosice could be 2021. There are reported technical complications to the section between Lietavska Lucka - Dubna Skala stretch with the Visnove tunnel near Zilina is experiencing complications. Work by the consortium of OHL and Vahostav on the D1 stretch Hubova – Ivachvova is suspended due
May 12, 2017 Read time: 1 min
Slovakia is reporting delays to works on the D1 motor, the country’s major east-west corridor and part of several pan-European routes, including the E50.


The planned 2020 completion of the D1 motorway linking Bratislava - Kosice could be 2021. There are reported technical complications to the section between Lietavska Lucka - Dubna Skala stretch with the Visnove tunnel near Zilina is experiencing complications.

Work by the consortium of 980 OHL and Vahostav on the D1 stretch Hubova – Ivachvova is suspended due to a land slide. Comlettion was to have been later this year, but this could be put back.

The D1 Hricovske Podhradie - Lietavska Lucka should be completed at the end of 2018.

European route E 50 runs from the France’s northern Atlantic naval port of Brest to Makhachkala, on the Caspian Sea in the Russian republic Dagestan.

For more information on companies in this article

Related Content

  • Delays ahead for Slovakia’s Visnove tunnel
    September 5, 2018
    Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022. The recent announcement came as the ministry agreed to an extension to the construction permit held by Salini Impregilo for work on the twin-tube tunnel. The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company NDS.
  • Slovakia: early 2017 restart for work on the Cebrat Tunnel
    May 27, 2016
    Roman Brecely, Slovakia’s transport minister, has said that construction of the 2km long motorway tunnel Cebrat near Ruzomberok could be resumed at the beginning of 2017. But the cost is expected to increase by around €100 million. He added that the government likely will seek European Union funding. Construction was halted a year ago over concerns about the possibility of landslides and other geological issues. For this reason, the tunnel route may alter and be an additional 1.5km longer. The tunn
  • Bratislava bypass and Karpaty tunnel completion set for 2030
    June 18, 2018
    Slovakia’s national motorway company NDS expects that the Bratislava bypass on the D4 motorway together with the Karpaty tunnel will be completed around 2030. The D4 motorway is part of the trans-European transport network and will connect with the planned R7 expressway linking western and eastern Slovakia, and the existing D1 and D2 motorways”. Apart from construction works on part of the D4 motorway, another two stretches are planned on this link, including the 3.6km stretch from Devinska Nova Ves t
  • Bratislava bypass and Karpaty tunnel completion set for 2030
    June 18, 2018
    Slovakia’s national motorway company NDS expects that the Bratislava bypass on the D4 motorway together with the Karpaty tunnel will be completed around 2030. The D4 motorway is part of the trans-European transport network and will connect with the planned R7 expressway linking western and eastern Slovakia, and the existing D1 and D2 motorways”. Apart from construction works on part of the D4 motorway, another two stretches are planned on this link, including the 3.6km stretch from Devinska Nova Ves t