Costa Rica road projects moving forward - slowly

Costa Rica is moving ahead with a series of major road projects, but progress is proving slower than anticipated or desired. The Costa Rica Government is struggling to achieve satisfactory progress with its overall road improvement programme. So far the key focus has been on maintaining existing links rather than building and improving road connections. The country’s National Laboratory for Structural Material and Models (Lanamme) has produced a report revealing that 85% of the national roads are in accepta
July 18, 2017 Read time: 3 mins
Costa Rica is moving ahead with a series of major road projects, but progress is proving slower than anticipated or desired. The Costa Rica Government is struggling to achieve satisfactory progress with its overall road improvement programme. So far the key focus has been on maintaining existing links rather than building and improving road connections. The country’s National Laboratory for Structural Material and Models (Lanamme) has produced a report revealing that 85% of the national roads are in acceptable condition. However the report also reveals that the Costa Rica Government is focussing on repairing roads instead of upgrading them significantly. Although Costa Rica has managed to increase the percentage of roads in good condition from 38% in 2015 to 48% at present, the country has many roads in need of major repairs according to the report. And some roads have merely been patched rather than having the major upgrades required according to the report.


Meanwhile uncertainty surrounds the start date for improvement works for a key stretch of road. The project to widen and upgrade Route 32 is being carried out by Chinese contractor China Harbour Engineering Company (CHEC). The timeline originally called for the construction work to commence in September 2017 but this may be put back to mid-2018. The contractor says that the land expropriation process has still to be completed while various licences have also to be procured, plans for moving utilities have to be completed and some stretches of the route may require archeological investigations. CHEC plans to deliver the project's final design to the national road authority, Consejo Nacional de Vialidad (2538 Conavi), on 15th August 2017. The project is being financed with a loan worth US$320 million from the Chinese Eximbank. A further $100 million for the work is being provided by the Costa Rica Government.

Problems also surround plans to build a 30km stretch of road linking Sifon, in San Ramon, with La Abundancia, in San Carlos. Costa Rica’s Treasury Inspector's Office (CGR) has not given approval for a $24.6 million increase in the value of a contract with Sanchez Carvajal. In addition CGR has also turned down a request for an extension to the time required for the work. CGR says that there are no assurances that the increased budget and time for the work will ensure its completion. Meanwhile Conavi has previously voiced its concern over the work, requesting a change to the contract and assurances that sufficient financing would be in place. The work was previously expected to cost $164 million but CGR now believes that the work will cost $213 million. The project has had a troubled past as work was originally started by a Taiwanese contractor in the third quarter of 2005. But the works hit problems and activity ceased in mid-2008, with Sanchez Carvajal then taking over the contract at a later date. The stretch from Sifon to La Abundancia forms the central section of a road new connection with San Carlos but the work has been afflicted by a series of delays arising from technical, financial and environmental challenges.

For more information on companies in this article

Related Content

  • Honduras is planning major road improvement works
    October 5, 2016
    Honduras is planning a series of major road improvement works. The focus of this road upgrade work will be improvements along the country’s Corredor Pacifico. The work is being planned by the Honduras Government and is expected to cost in excess of US$244.5 million. Financing is being provided by the Inter-American Development Bank (IADB) for work on the 137km stretch of road from Choluteca to El Amatillo, which will cost around $154 million. Meanwhile the 87.5km stretch from Tegucigalpa-Jicaro Galan is exp
  • Romania building new road and highway links
    July 19, 2016
    Romania’s road building programme is moving forward, but perhaps more slowly than the country’s National Company for Highways and Roads (CNADNR) would prefer. At present a total of 733km of highways are open to use in Romania, but new sections measuring up to 260km in all should be ready for traffic by the end of 2017. A further 22km of the A1 highway connecting Orastie with Sibiu is expected to open in the third quarter of 2016. The Deva to Lugoj stretch of the A1 has also to be completed, while a section
  • Scottish dual carriageway work facing delays
    February 9, 2021
    Two Scottish dual carriageway projects are facing delays.
  • Russia's key highway development project
    February 8, 2012
    One of the largest construction programmes in Europe is being carried out to get a Russian resort ready for the Winter Olympics. Patrick Smith reports