Romania building new road and highway links

Romania’s road building programme is moving forward, but perhaps more slowly than the country’s National Company for Highways and Roads (CNADNR) would prefer. At present a total of 733km of highways are open to use in Romania, but new sections measuring up to 260km in all should be ready for traffic by the end of 2017. A further 22km of the A1 highway connecting Orastie with Sibiu is expected to open in the third quarter of 2016. The Deva to Lugoj stretch of the A1 has also to be completed, while a section
July 19, 2016 Read time: 2 mins
Romania’s road building programme is moving forward, but perhaps more slowly than the country’s National Company for Highways and Roads (2870 CNADNR) would prefer. At present a total of 733km of highways are open to use in Romania, but new sections measuring up to 260km in all should be ready for traffic by the end of 2017. A further 22km of the A1 highway connecting Orastie with Sibiu is expected to open in the third quarter of 2016. The Deva to Lugoj stretch of the A1 has also to be completed, while a section of highway from Sibiu to Pitesti also remains to be upgraded. A 47km section of the A3 highway from Campia Turzii to Targu Mures is amongst the stretches due for completion, as is the 30km stretch of the A3 from Bors to Suplacu and the junction of the A3 at capital Bucharest. Sections of the Transiva Highway from Mihaiesti to Nadaselu and Gilau to Nadaselu measuring 17km and 9km respectively should also be ready for traffic by the end of 2017.

Other major road projects CNADNR is working on include the new ringroad around Bucharest, due for completion at the end of 2018, as well as upgrades to various national roads.

For more information on companies in this article

Related Content

  • Romania picks four for Campia Turzii to Ogra-Targu Mures highway
    February 3, 2015
    Romania’s National Company for Highways has selected four joint ventures to build the 56.5km Campia Turzii - Ogra-Targu Mures highway, costing around €268 million (US$303 million). Strabag of Austria and Straco of Romania will build the two sections, while Straco will join forces with Specialist Consulting and Total Road to build another section. Lemacons, Vega 93 and Arcada will build the Targu-Mures-Ungheni section, the last stretch. The four Campia Turzii to Ogra-Targu Mures highway is part of the A3
  • Romania retenders Lugoj-Deva section of A1
    April 20, 2022
    The Lugoj-Deva segment has been troublesome, with landslides halting work at least twice.
  • Romania sets out road programme openings for 2019
    January 11, 2019
    Romania will open nearly 44km of new roads in 2019, including parts of the A1 Motorway between Deva and Lugoj. Also to be opened are an 8km stretch between Sebes and Alba Iulia Sud as well as an 18km section of the A3 Motorway between Chetani and Iernut. CNAIR – the National Road Management Infrastructure Company - estimates that drivers will be able to make use of 925km of high-speed motorways in Romania by the end of 2019, around 120km more than at present. Last summer, Romania’s transport minist
  • Romania’s road expansion plan
    July 9, 2024
    Romania is planning a major road expansion programme.