Colombia’s La Linea Tunnel project delayed

A tale of woe surrounds Colombia’s La Linea Tunnel project, which is still incomplete. The project has been beset by a serious of issues including unexpectedly poor geological conditions, contractors having the wrong kind of insurance, insufficient funds for work to continue and in more recent times, further geological problems. While the Tolima end of the link is now close to completion, work still remains to be done at the Quindio end of the tunnel. Measuring 315m long, the La Gata section is now largely
August 22, 2018 Read time: 2 mins

A tale of woe surrounds Colombia’s La Linea Tunnel project, which is still incomplete. The project has been beset by a serious of issues including unexpectedly poor geological conditions, contractors having the wrong kind of insurance, insufficient funds for work to continue and in more recent times, further geological problems.

While the Tolima end of the link is now close to completion, work still remains to be done at the Quindio end of the tunnel. Measuring 315m long, the La Gata section is now largely finished. However geological problems with the 165m El Viento section are not likely to be resolved until the end of 2018.

Surfacing work remains to be carried out while installation of some of the steel support arches is running behind schedule. The surfacing work should be complete by May 2019. The ventilation, lighting and traffic control systems have yet to be installed.

Related Content

  • Colombia tunnel delays continue
    September 26, 2016
    Further delays have hit the project to build the La Linea Road Tunnel in Colombia. As a result the tunnel will not be open to traffic until the first half of 2018. This is the latest in a series of delays that have held back the opening of the tunnel. Previous delays have been caused by the discovery of geological conditions that were far more challenging than originally expected as well as problems over insurance cover for the construction firms. When open to traffic the new link will stretch 8.6km and wil
  • Further delays possible for Colombia tunnel
    July 21, 2016
    Further delays to completion look a possibility for Colombia’s La Linea Tunnel project. A strike by truck drivers meant that supplies of construction materials were halted, adding to previous delays. The country’s National Road Institute (Invias) has stated that work on the tunnel does not look likely to be finished until the first quarter of 2017. The project will only be completed before that date if faster progress can be achieved with the electro-mechanical works currently in hand. Invias has previously
  • Colombian highway connections under construction
    April 9, 2014
    In Colombia work on the dual carriageway connecting Bogota and Buenaventura is now 40% complete. The link should be complete by the end of 2016. The Bogota-Girardot road is now opening, with excavation work still underway on the La Linea tunnel. The tunnel section of the project has been subject to delays arising from geological issues but when it is open, the tunnel will cut travel times and also improve safety over the existing route. The driving of the tunnel should be complete by September 2014 with the
  • Colombia tunnel construction cost climbs
    January 25, 2018
    Work on the La Linea Tunnel project in Colombia has cost considerably more than first anticipated. The National Road Institute (Invias) says that the bill so far tops US$774 million. Extra costs of around $281.5 million have been incurred due to the need to drive a pilot tunnel as well as for three additional tunnel stretches as well as bridges along the approaches to the main tunnel. The project is now expected to be complete by the end of 2018, somewhat later than originally expected.