Chile’s Chacao Bridge project - futuresecured

Chile’s landmark Chacao Bridge project now looks to be back on a sound footing, with completion expected in late 2022 or early 2023. This projects for the 2.6km-long bridge was to have been built jointly by Brazilian firm OAS and South Korean company Hyundai. However OAS hit financial difficulties and had to withdraw from the project. As a result, Hyundai will now buy the 49% stake OAS had in the project. As Hyundai already has a 51% stake in the bridge project, this will give the firm total ownership ove
July 19, 2018 Read time: 2 mins
Chile’s landmark Chacao Bridge project now looks to be back on a sound footing, with completion expected in late 2022 or early 2023.


This projects for the 2.6km-long bridge was to have been built jointly by Brazilian firm 1511 OAS and South Korean company 236 Hyundai. However OAS hit financial difficulties and had to withdraw from the project. As a result, Hyundai will now buy the 49% stake OAS had in the project. As Hyundai already has a 51% stake in the bridge project, this will give the firm total ownership over the works.

The project has been subject to a number of delays and an earlier plan was cancelled at a fairly late stage over cost concerns. The new bridge will be a suspension type structure designed to cope with the often severe earthquakes in the area. It is also being designed and constructed to cope with high winds (of up to 240km/h) and strong sea currents that also occur in the area.

Building the bridge will provide an important transport link to Chiloe Island, providing a key economic boost to the area in terms of tourism and trade. The new bridge will replace the current ferry traffic on which the islanders rely, cutting travel times to just three minutes compared with the 25-45 minutes that the ferry crossing involves.

For more information on companies in this article

Related Content

  • Chile’s Chacao Bridge under construction
    March 6, 2018
    Construction work on Chile’s Chacao Bridge project is now underway. The 2.75km suspension bridge will connect the Chilean mainland with Chiloe Island. The bridge structure has been designed to flex so that It can cope with severe earthquakes, which present a risk in the area. The project is costing US$700 million to carry out with South Korean company Hyundai heading the construction. Building the link should take around five years with its completion set for 2023, although the work could be finished earlie
  • Delays have hit Chile’s Chacao Bridge project
    August 28, 2013
    Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
  • Hyundai looking for new partner for Chilean bridge deal
    March 21, 2016
    South Korean firm Hyundai is looking for a new partner to join the consortium that will construct Chile’s Chacao Bridge. The project has been planned for some years, having been cancelled once previously, and will connect with Chiloe Island, replacing the current ferry service. The new partner for the consortium would take the place of Brazilian firm OAS, which is currently embroiled in legal difficulties due to an ongoing investigation in Brazil. The aim is that a new partner could buy out the 49% stake in
  • Chilean bridge project to Chiloe Island delayed
    October 31, 2018
    Delays to the project to construct Chile’s Chacao Bridge mean that an additional two years may be required for the work. The work is now being carried out solely by a consortium, Consorcio Puente Chacao, headed by the South Korean contractor Hyundai.