Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with C
August 28, 2013 Read time: 2 mins
Delays now look likely to affect the construction programme for Chile’s Chacao Bridge project. The US$740 million bridge project, long in planning, has been delayed on previous occasions for a number of reasons. The tolled link will connect Chiloé Island with the Chilean mainland in its Region X once complete. This 2.6km link will become South America’s largest suspension bridge although its opening will reduce journey times considerably over 25-45 minutes taken by the ferries used at present to link with Chiloé Island over the Chacao Channel. According to Chile's public works ministry, MOP, has moved back the tender process for the project towards the end of 2013.

The concession should be awarded in early 2014 with construction work itself commencing in 2015 and the structure opening to traffic in 2019. Eight consortia pre-qualified for the tender process. These are: Isei Joint Venture, Constructora Puente Chacao (CPC), 3959 Sacyr Samsung 3220 Parsons Puente Chacao, Consorcio Puelche, China Railwaygroup Limited, 3366 China Road and Bridge Corporation, Consorcio Cai Cai Vilu and Consorcio 1511 OAS-236 Hyundai-5549 Systra-Aas Jakobsenv.

Work on the bridge was original supposed to start in 2007 with its opening planned for 2012. However, a substantial increase in the costs estimated by the project team of designer and contractor showed that the price would exceed the limit imposed by the 968 Chilean Government. The project was cancelled, prompting an outcry from those on the island and was then revived in 2009 as a fall in the cost of steel made it economically feasible once more.

For more information on companies in this article

Related Content

  • Chile’s Chacao bridge project generates just one consortium technical bid
    November 8, 2013
    Only one consortium has submitted a technical bid in the tender for a project to build the Chacao bridge in Chile. The bridge will link Chiloe island with Chile’s mainland Los Lagos region. The Chilean government has earmarked a maximum project budget of US$740 million. The consortium that has submitted the technical bid, which would see the construction of a four-lane bridge, is made up of Hyundai of South Korea, Systra of France, Brazilian company OAS and Aas-Jakobsen of Norway. The consortium has
  • Progress being made for key Chile mega projects
    February 22, 2016
    Progress is being made in Chile for two key mega projects, the Chacao Bridge and the El Melon Tunnel. Chile's Ministry of Public Works (MOP) has ordered the consortium working on the Chacao Bridge project to carry out additional studies. The consortium comprises Systra, OAS, Aas-Jakobsen and Hyundai and the project is worth US$511.45 million. The consortium has to respond to observations made by the MOP on the design proposal presented in August 2014. The works to build the bridge now look likely to continu
  • Chile choses Chacao Chiloe crossing consortium
    December 12, 2013
    The Chilean authorities have awarded the project to build the Chacao crossing to a consortium comprising OAS, Hyundai, Systra and Aas-Jakobsen. The winning bid was for US$680.4 million. When the contracting consortium completes construction of Chile’s Chacao Channel crossing it will connect Chiloe Island to Chile’s mainland. The project has been halted and delayed a number of times over the years but this move will see the work going ahead at last, with construction expected to take some 79 months.
  • Spanish firms interested in US$740mn Chile bridge project
    June 5, 2013
    Spanish companies Sacyr, ACS and OHL will take part in three of the consortia that will bid in the US$740 million contract to build the longest suspension bridge in Chile. Works for the 2.5km Chacao Bridge, connecting the island of Chiloe and Chile's coast line, are expected to be awarded during the first quarter of 2014, with construction due to begin in 2015.