ANI transfers operation of Guillermo Gaviria Correa to Mar 1 Devimar

The Colombian department of Antioquia has transferred operation of the Guillermo Gaviria Correa road connection to the National Infrastructure Agency (ANI). ANI will, in turn, cede the concession to the Mar 1 Devimar consortium. The road, named after the assassinated governor of Antioquia, runs between the municipalities of Medellin and San Jerónimo and connects Medellin to the Uraba Gulf, part of the Caribbean Sea. Gaviria, a Nobel Peace Prize nominee, was kidnapped by guerrillas and held captive for
July 6, 2016 Read time: 2 mins
The Colombian department of Antioquia has transferred operation of the Guillermo Gaviria Correa road connection to the National Infrastructure Agency (ANI).

ANI will, in turn, cede the concession to the Mar 1 Devimar consortium.

The road, named after the assassinated governor of Antioquia, runs between the municipalities of Medellin and San Jerónimo and connects Medellin to the Uraba Gulf, part of the Caribbean Sea. Gaviria, a Nobel Peace Prize nominee, was kidnapped by guerrillas and held captive for a year before being among 10 people killed in 2003 in response to an attempted military rescue.

In operation since 2007, the highway, in combination with the Fernando Gómez Martínez tunnel – the longest tunnel in South America - has done away with the curvy roads once commonplace in the tourist areas of Santa Fé de Antioquia, San Jerónimo and Sopetrán.

The Mar 1 Devimar consortium will soon start construction of the Mar 1 motorway, one of the main projects included in the federal government's 4G Roads Programme. The contract for construction of the 176km Mar 1 was awarded in 2015. The road will connect with the El Toyo tunnel and Mar 2 motorway at a cost of around US$500 million. Work will include construction of 17 tunnels and 41 bridges, as well as a second lane in the Medellin-Santa Fe section and refurbishment of Bolombolo-Santa Fe section.

Meanwhile, the president of the National Infrastructure Agency (ANI), Luis Fernando Andrade, said that there is a six-month delay in achieving financial closures for the first phase of the government's 4G Road Programme. There are, however, 12 projects in the first stage of the process, which involves letters of commitment delivered to ANI by the investors.

Andrade said that financial closures for the remaining projects are likely to be ready in the near future, apart from the Mulalo-Loboguerrero motorway in Valle del Cauca department.

Related Content

  • Challenging Colombian tunnel completed
    May 30, 2024
    A tunnel stretch on Colombia’s Santa Fe - Cañasgordas highway is complete – Mauro Nogarin reports
  • New Colombia highway link being built
    February 27, 2018
    A consortium of Colombian construction companies, Concesionaria Desarrollo Vial al Mar (Devimar), is to build the new in Autopista al Mar 1 highway. This 176km link is expected to cost US$790.5 million to build, connecting Medellin with Santa Fe de Antioquia. The new highway will cut journey times on the route by 20-30 minutes, boosting transport for the region. The project is complex and involves the construction of no less than 39 bridges, of which 26 will be situated between the 4.6km Tunel de
  • FCC heads group that will build Toyo Tunnel in Colombia
    November 6, 2015
    Spanish environmental services, infrastructure and water group FCC has secured a €392 deal to design, build, operate and maintain the 10km Toyo Tunnel in Urabá Port, Colombia. The Government of Antioquia awarded the project to the consortium in which Madrid-based FCC has a 40% share and a group of local business people hold 60%. The tunnel is around 80km from Medellin, the capital of Colombia’s mountainous Antioquia province. The US$426 million contract is for 10 years, during which design and constru
  • Colombia tunnel construction contract commencing
    February 5, 2018
    Driving work has commenced for Colombia’s Toro Tunnel project. The tunnel will measure 9.8km long and is located in Colombia’s Antioquia Department, with the completion expected in 2022. The project is costing US$650.5 million and the link is intended to provide a link between the Autopista al Mar 1 and Autopista al Mar 2 highways. When complete the tunnel will also cut the travel time between Medellin and Uraba to four hours.