Concrete pumps speed busy road upgrade

WORK ON a major upgrade at a busy German road junction is expected to be completed by the end of 2011. To assist in the project, two Putzmeister large-boom concrete pumps, an M 58-5 from Berger Beton and an M 62-6 from BFM Betonförderdienst in Munich, arrived at the Neufahrn motorway junction, north of the city. The junction, when viewed from above, looks like a flatly pressed four-leaf clover, and can no longer cope with traffic volumes. Two national motorways, the A 9 and the A 92, intersect at the
February 14, 2012 Read time: 3 mins
Concreting is carried out with traffic flowing freely under the bridge construction. The Putzmeister M 58-5 pump is seen on the north-eastern ramp during construction
WORK ON a major upgrade at a busy German road junction is expected to be completed by the end of 2011.

To assist in the project, two 1259 Putzmeister large-boom concrete pumps, an M 58-5 from Berger Beton and an M 62-6 from BFM Betonförderdienst in Munich, arrived at the Neufahrn motorway junction, north of the city.

The junction, when viewed from above, looks like a flatly pressed four-leaf clover, and can no longer cope with traffic volumes. Two national motorways, the A 9 and the A 92, intersect at the junction, and along with the Munich motorway ring road (A 99) and the A 8 Ulm-Munich-Salzburg, the A 9 is the most important north-south route, especially for domestic and international commercial and holiday traffic.

The A 92 connects Munich with its airport and is also important for Eastern European traffic.

The average volume of traffic from the airport towards Munich is currently approximately 24,000/day, with the average daily traffic flow predicted to increase to about 38,000/day by 2020, meaning some 1,600 vehicles/hour using the Neufahrn junction, along with rush-hour traffic.

In view of this projection, the only option is a speedy connection via the existing motorway junction using a direct ramp. The current singlelane exit via a quadrant of the clover is being completely replaced by a two-lane flyover to channel traffic from the A 92 to the A 9 towards the south.

The customer is Autobahndirektion Südbayern and the contractor is Hentschke Bau in Bautzen.

Construction work at the junction started in April 2009 with the reconstruction of a connecting ramp and the spillage that is required to build the new bridge, with 110,000m³ of delivered soil. In 2010, comprehensive excavation and ceiling work took place at the Neufahrn junction as well as bridge construction work in the whole area.

At the flyover, concreting of the first 120m section was completed in October, 2010, and this was followed by the 80m-long section two scaffolding work carried out at night.

Each of the two Putzmeister truck-mounted concrete pumps was fully-supported at the foot of one of the construction columns within one of the northern clover quadrants of the motorway junction. From this location, they pumped concrete to the concrete placement sites on the approximately 12m high bridge, while traffic flowed freely on the circular paths of the exits and under the structure.

Concreting started at 6am, with the two truck-mounted concrete pumps standing fullysupported at the foot of one of the construction columns within one of the northern clover quadrants of the motorway junction. From this location, they pump concrete to the sites of concrete placement on the approx. 12m high bridge.

Meanwhile, the traffic flows freely on the circular paths of the exits and under the structure.

The complete superstructure contains 3,400m³ of concrete, and so that traffic can travel on the road comfortably and safely, the finished concrete surface receives another 8cm thick layer to the overall construction.

The concrete is first primed and completely sealed using epoxy resin. An asphalt sheeting (0.5cm) comes next and then a protective layer of mastic asphalt (3.5cm thick). Finally, the surface of the road is formed by a 4cm surface layer of stone mastic asphalt.

For more information on companies in this article

Related Content

  • Increasing importance of alternate truck routes
    February 14, 2012
    The fabled Silk Route from China to Europe takes many forms, and is again becoming increasingly important as Patrick Smithreports The ancient Silk Road was never a single caravan route, but covered hundreds of kilometres in width extending in length for around 10,000km. This is the view of the European International Road Transport Union (IRU), and many other countries and organisations, who point out that it is a system of routes covering many countries via a series of branch roads that dates back some 2
  • Road markings - simple, effective guidance
    February 15, 2012
    Road markings as a simple yet extremely effective method of guiding motorists safely on the world's road. Patrick Smith reports. Road markings are as important as road signs and give information about the roads being travelled on and actions that drivers should or should not be taking. For example, in many instances white lines often tell motorists something about the road: longitudinal lines can warn of situations that require action such as turn right, left or do not cross. Transverse lines often mean giv
  • Power Curbers ramps up Florida projects
    September 5, 2022
    A Florida company is using Power Curbers machines for major runway work in the US state.
  • Epoxy for Ethiopia
    March 10, 2022
    Paving trials using epoxy resins in the Netherlands and New Zealand could lead to similar paving in Ethiopia, reports Kristina Smith.