Concrete pumps speed busy road upgrade

WORK ON a major upgrade at a busy German road junction is expected to be completed by the end of 2011. To assist in the project, two Putzmeister large-boom concrete pumps, an M 58-5 from Berger Beton and an M 62-6 from BFM Betonförderdienst in Munich, arrived at the Neufahrn motorway junction, north of the city. The junction, when viewed from above, looks like a flatly pressed four-leaf clover, and can no longer cope with traffic volumes. Two national motorways, the A 9 and the A 92, intersect at the
February 14, 2012 Read time: 3 mins
Concreting is carried out with traffic flowing freely under the bridge construction. The Putzmeister M 58-5 pump is seen on the north-eastern ramp during construction
WORK ON a major upgrade at a busy German road junction is expected to be completed by the end of 2011.

To assist in the project, two 1259 Putzmeister large-boom concrete pumps, an M 58-5 from Berger Beton and an M 62-6 from BFM Betonförderdienst in Munich, arrived at the Neufahrn motorway junction, north of the city.

The junction, when viewed from above, looks like a flatly pressed four-leaf clover, and can no longer cope with traffic volumes. Two national motorways, the A 9 and the A 92, intersect at the junction, and along with the Munich motorway ring road (A 99) and the A 8 Ulm-Munich-Salzburg, the A 9 is the most important north-south route, especially for domestic and international commercial and holiday traffic.

The A 92 connects Munich with its airport and is also important for Eastern European traffic.

The average volume of traffic from the airport towards Munich is currently approximately 24,000/day, with the average daily traffic flow predicted to increase to about 38,000/day by 2020, meaning some 1,600 vehicles/hour using the Neufahrn junction, along with rush-hour traffic.

In view of this projection, the only option is a speedy connection via the existing motorway junction using a direct ramp. The current singlelane exit via a quadrant of the clover is being completely replaced by a two-lane flyover to channel traffic from the A 92 to the A 9 towards the south.

The customer is Autobahndirektion Südbayern and the contractor is Hentschke Bau in Bautzen.

Construction work at the junction started in April 2009 with the reconstruction of a connecting ramp and the spillage that is required to build the new bridge, with 110,000m³ of delivered soil. In 2010, comprehensive excavation and ceiling work took place at the Neufahrn junction as well as bridge construction work in the whole area.

At the flyover, concreting of the first 120m section was completed in October, 2010, and this was followed by the 80m-long section two scaffolding work carried out at night.

Each of the two Putzmeister truck-mounted concrete pumps was fully-supported at the foot of one of the construction columns within one of the northern clover quadrants of the motorway junction. From this location, they pumped concrete to the concrete placement sites on the approximately 12m high bridge, while traffic flowed freely on the circular paths of the exits and under the structure.

Concreting started at 6am, with the two truck-mounted concrete pumps standing fullysupported at the foot of one of the construction columns within one of the northern clover quadrants of the motorway junction. From this location, they pump concrete to the sites of concrete placement on the approx. 12m high bridge.

Meanwhile, the traffic flows freely on the circular paths of the exits and under the structure.

The complete superstructure contains 3,400m³ of concrete, and so that traffic can travel on the road comfortably and safely, the finished concrete surface receives another 8cm thick layer to the overall construction.

The concrete is first primed and completely sealed using epoxy resin. An asphalt sheeting (0.5cm) comes next and then a protective layer of mastic asphalt (3.5cm thick). Finally, the surface of the road is formed by a 4cm surface layer of stone mastic asphalt.

For more information on companies in this article

Related Content

  • Speedy repair for key UK motorway
    October 2, 2014
    Major road repairs have been carried out on the UK’s busy M25 motorway. Stirling Lloyd's Safetrack Crack Infill is helping to reinstate major sections of London's M25 orbital motorway.
  • Japan investing in Ugandan roads
    January 31, 2014
    Japanese investment is helping develop Ugandan infrastructure. Construction of the New Nile Bridge is being part-financed by the Japanese Government. Some US$90 million for the dual-lane bridge is being provided through the Japan International Cooperation Agency (JICA). The bridge forms part of the important Northern Transport Corridor of East Africa, which runs from the Port of Mombasa in Kenya through Uganda, Rwanda, Burundi to the Democratic Republic of Congo. This route is vital for Uganda’s economy, as
  • Nepal bridge building receiving funding
    June 4, 2018
    Financing from the World Bank will help pay for bridge building work in Nepal. The road from Muglin to Narayanghat is being widened currently, which will see the route featuring a lane in either direction, rather than the single lane that carries all traffic at present. This will boost its capacity and reduce delays to drivers on the route, which carries around 20,000 vehicles/day. Improving the 36km, north-south route however requires the construction of 18 new bridges. Much of the route is already surface
  • Cifa gets pumped over final work on Milan bypass
    May 14, 2015
    Truck-mounted concrete pumps from the manufacturer Cifa have been working around the clock at one of Italy’s most prestigious road infrastructure projects, the Milan Outer Bypass. The toll motorway project, known by the TEEM acronym from the Italian name Tangenziale Est Esterna di Milano, involves 32km of new carriageway consisting of three lanes in each direction in addition to an emergency lane. The route winds through agricultural land and connects the A4 highway (Milano-Venezia) in the north to the A