Pocitelj Bridge reaches banks of Neretva River

Contractors are working to correct a concrete issue on a section of the 100m-long continuous prestressed girder bridge across the Neretva River in Bosnia and Herzegovina.
By David Arminas August 21, 2023 Read time: 2 mins
The Počitelj Bridge, now reaching both banks of the Neretva River, is the largest bridge on the entire pan-European Corridor 5c highway (image courtesy JP Autocesta FbiH – Bosnia and Herzegovina’s motorways agency)

Contractors building the Pocitelj Bridge over the Neretva River in Bosnia are examining damage to a bridge segment that appeared during prestressing of cables.

A crack was discovered on a 4.75m-long segment of deck along the nearly 1km-long structure that rises 100m above the river, according to media reports. Few other details were given.

The bridge is being built by a consortium of Azerbajan construction group Azvirt and Chinese state-owned hydropower engineering and construction companies Sinohydro and Powerchina Roadbridge Group. Hering d.d. Široki Brijeg is a subcontractor and overall construction supervision of the entire Počitelj - Zvirovići motorway is by the Italian group IRD Engineering.

The client, JP Autocesta FbiH – Bosnia and Herzegovina’s motorways agency – has held meeting with the contractors to establish corrective work, the newspaper said. The agency also noted that remedying construction issues at the end of works on such complex structures was normal and all partners are cooperating fully to correct the problem.

In July, the Sarajevo Times reported that work on the final span had been completed allowing connection of the bridge to both banks of the river. Testing and finishing of the decks is now underway for an anticipated opening by the end of the year.

The Počitelj Bridge is the largest bridge on the entire pan-European Corridor 5c highway. The concrete bridge is designed as a continuous prestressed girder bridge with five spans of 147m in length and two connecting side spans of 105m. The box cross-section structure is built by the free cantilever construction method.

Around 38,000m³ concrete, 9,000 tonnes of reinforcement and 1,500 tonnes of prestressing cables were used. Meanwhile, around 20,000m² of asphalt and waterproofing will be installed along the 22m-wide deck in the coming period.

“With the near completion of activities on the Pocitelj – Zvirovici section and the start of construction work on the Prenj tunnel and the Mostar north – Mostar south section and the Kvanj – Buna tunnel, which we plan to contract this year, we are opening new perspectives for the business community and raising the economic potential of this part of Bosnia and Herzegovina (BiH) to a higher level,” said Denis Lasic, acting director of JP Autocesta FbiH.

Related Content

  • New version of world’s longest floating bridge
    August 12, 2014
    The creation of a new version of the world’s longest floating bridge in Seattle, in the US state of Washington, is among the world’s most eye-catching current bridge engineering projects. It is an impressive example of the health of the bridge replacement sector, particularly in the US, leaving it well placed for growth. Guy Woodford reports Already the world’s longest floating bridge at over 2,310m long, the Governor Albert D Rosellini-Evergreen Point Floating Bridge in Seattle in the United States is g
  • Key expressway route through Hunter Valley
    November 11, 2013
    Australia’s Hunter Valley will benefit from a new high speed expressway, which is currently under construction - Simon Gould reports Located two hours north of Sydney, the Hunter Valley region in New South Wales is one of Australia’s largest producers of coal and wine. With international demand, particularly from Asia, for both continuing to increase, a significant upgrade of infrastructure was required between the region and the port of Newcastle, the world’s largest coal export port. However the strict en
  • Doka’s Voest Bridge bypass project
    February 10, 2020
    The Voest Bridge over the Danube River is part of the A7 Mühlkreis Autobahn through Linz, Austria, is 40 years. Two bypass bridges are being constructed alongside the existing cable-stayed bridge as part of the client ASFINAG’s strategy to boost traffic capacity - around 100,000 vehicles cross the old bridge each day.
  • IFC to provide consultancy on three-section Corridor Vc works
    May 3, 2013
    JP Autoceste FBiH, the state-owned motorway company of Bosnia's Muslim–Croat Federation, has revealed that the International Finance Corporation (IFC) will provide consultancy for finding a private partner for three sections of Corridor Vc. The IFC consultancy-covered sections are Doboj Jug (Karusa)-Medakovo (4km); Medakovo-Ozimica (21km); and Ozimica-Poprikusa (13.7km). The consultancy deal will last for a period of 15 months during which a due diligence of costs and a study for the three Corridor Vc secti