The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany.
February 29, 2012 Read time: 3 mins
The BOMAG milling machines worked reliably within a tight time frame
The Frankfurt/Hahn Airport is benefiting from an upgrade to its facilities as well as its road links that will help cope with increased traffic. The site was commissioned as a civilian airport in 1993 and is one of the fastest growing German airports as well as being the fourth largest cargo airport in Germany. Upgrade work to the B50 Bundestrasse that connects with the airport is of prime importance and contractor Beitz-Fräsdienstleistungen is widening a 7.5km section of the road. The work will see the road widened and upgraded from two lanes to four-lane and this has been speeded by the high productivity of 172 Bomag planing equipment.

The work was carried out in three different stages with the first stage being planing to a depth of 40mm over a length of 7.5km, an area of 50,000m2. This work removed around 4,500tonnes of material and 180 truck loads were required to haul the milled cuttings away. The second stage was the milling of another 4,500m2 of surface to improve weak points in the road structure, which removed 1,350tonnes of binder and base layers and required a further 55 truck loads to haul the material away. The third and final stage of the milling job was to remove a 150m stretch of 6m wide binder and base layers to a depth of 320mm in front of bridges and this required the removal of 700tonnes of material in a further 28 trucks. In all the milling work required some 6,550tonnes of material to be removed.

The work had to be finished within a tight time frame and the BOMAG BM 2000/60 cold planers worked reliably and productively within the schedule. The planing work had to be completed within a single week during the day from 06.30-17.00 and with a public holiday on the Thursday, the time frame was tighter still. In spite of the surface layer being hard and only a few years old, an average milling speed of 25 m/min was achieved over the 7.5km during the first stage of the planing work. This gave a perfect, clean planed surface that allowed for quick, precise re-laying of the new surface and reduced the time needed for sweeping the road afterwards. During all three stages the average fuel consumption was an encouraging 60-65litres/hour, while cutter wear was minimised due to the effective water spraying system for the planer. Productivity was further boosted by the automatic settings that returned the cutting depth to the same height when each truck carrying the milled material was moved into place under the discharge conveyor.

For more information on companies in this article

Related Content

  • Race circuit milling job with machine control
    June 20, 2017
    The Misano racetrack in Italy has benefited from the use of the latest milling technology to deliver a new surface. Contractor Pesaresi Giuseppe decided to take advantage of the cutting-edge technologies of Wirtgen and Trimble. In less than three weeks, all irregularities were removed from the track, leaving it ready for motor sports racing. When the call for tender was issued to modernise the track, the construction of two new track sections was also planned. These plans included measures to boost safety
  • Smoother highway achieved in Florida
    June 16, 2016
    The busy I-10 in Florida is now benefiting from a smoother surface, following very necessary reconstruction work. There were no completed sections of I-10 until 1961 when the 59km Sanderson to Jacksonville stretch was first finished. In the years since, section by section have been constructed, culminating in the complete stretch of I-10 in Florida, running 579km through the state. The interstate stretches west well beyond the Florida border making I-10 one of three coast-to-coast interstates, along with
  • Asphalt paving review for 2019
    February 12, 2020
    A series of new asphalt pavers have been introduced in 2019
  • Wirtgen machines help stabilise industrial area in Germany
    May 13, 2015
    Equipment from the Wirtgen Group has played an important role in stabilising the area being developed for a new industrial zone in Germany. The site of a new factory located in Backnang, including access roads and parking areas has seen the use of the Wirtgen machines to help address poor ground conditions. The contractor employed a Wirtgen WR 200i soil stabiliser, two Hamm compactors and a Streumaster SW 16 MC binding agent spreader to improve the ground properties the soil. The firm, Riva, expanded