The busy I-10 in Florida is now benefiting from a smoother surface, following very necessary reconstruction work. There were no completed sections of I-10 until 1961 when the 59km Sanderson to Jacksonville stretch was first finished. In the years since, section by section have been constructed, culminating in the complete stretch of I-10 in Florida, running 579km through the state. The interstate stretches west well beyond the Florida border making I-10 one of three coast-to-coast interstates, along with
June 16, 2016 Read time: 4 mins
The Florida job won an award for the high quality results achieved
The busy I-10 in Florida is now benefiting from a smoother surface, following very necessary reconstruction work. There were no completed sections of I-10 until 1961 when the 59km Sanderson to Jacksonville stretch was first finished. In the years since, section by section have been constructed, culminating in the complete stretch of I-10 in Florida, running 579km through the state.

The interstate stretches west well beyond the Florida border making I-10 one of three coast-to-coast interstates, along with I-80 and I-90. In 2015, the 2697 Florida Department of Transportation (FDOT) awarded the complete rehab of a 13km section of I-10 between Tallahassee and Monticello, Florida. The traffic load has steadily increased over the years.

Contractor Peavy and Son Construction won the bid for full-depth milling and paving but the stretch needed extensive work as it had last been worked on around 15 years earlier and the surface was in poor shape. The contractor had a 120-day deadline to complete the project. In addition to the poor road condition, the contractor had the challenge of working on a well-travelled road with hills, curves and elevations, as well as width variations of up to 150mm along the outside shoulder edge.

The contractor checked with FDOT to see if it should follow the existing road irregularities or correct it and provide a consistent finished edge. FDOT opted for the corrected road width. The firm then used its highway-class 1252 Roadtec RX-900e to mill a depth of 82.5mm.

A total of 17,558m2 of milled material was trucked out with most being converted to RAP.    Three lifts of hot-mix asphalt (HMA) were placed using a Roadtec RP-190e rubber-tyred paver designed for highway work. The paver is equipped with a 2599 Carlson EZIV Rear Mount Screed and a 1228 MOBA-Matic II grade and slope control system, which adjusts the height and slope of the paver screed and adjusts the paving output of the machine to prevent paving too little or too much material, increasing paving quality and planarity.
Two lifts of structural asphalt were placed with a finishing friction course on top. The first structural asphalt course was 4,510tonnes of Traffic Level B HMA with no polymers. Then 2,526tonnes of Traffic Level D HMA with polymers was placed. A final 7,216tonnes of FC-5 open-graded friction course HMA provided the final traffic surface.

HMA traffic levels are graded A through E based on the design life of the pavement where Level A equals low traffic and Level E equals high traffic. The grading is based on the rate of pavement deterioration from the estimated number of 8.165tonne equivalent single-axle loads (ESALs). For any time period, ESALs on the most heavily travelled lane are estimated using the total traffic for a time period, the percentages of single unit trucks and combination trucks on the road, an equivalent load factor and a lane-load adjustment factor.

Choosing the right HMA is designed to ensure the longest life of a road before maintenance is required. Peavy and Son Construction has its own 1250 Astec HMA production plant, which is located approximately 32km from the job site. The company relied on its Roadtec MTV-1000 material transfer vehicle, which is designed for transferring while re-blending paving material to allow for continuous in-line paving.  

The company finished the I-10 rehab project before the 120 day deadline and FDOT then conducted laser profile measurements, which showed that the road’s smoothness and rideability were dead on.     In terms of quality of smoothness, the finished road received an average IRI (International Roughness Index) score of 32, which is well below the max rating of 48 assigned by the state. The quality of the road earned a 3% bonus plus additional incentive pay.

As a result, the Peavy and Son Construction I-10 work received FDOT’s “Smoothest Pavement of the Year Award” in the Limited Access Roadway category for 2014. Annually FDOT considers all the roadwork completed in the entire state for the year and awards a winner and a runner up based on finished quality for two categories of roads, Primary Roadway and Limited Access Roadway.

For more information on companies in this article

Related Content

  • Milling and paving for a highway repair in Oklahoma
    April 5, 2017
    Milling and paving work has helped restore the road surface on an important stretch of highway in the US state of Oklahoma. US Highway 62 is a key route, running 3,597km from to Niagara Falls, New York, at the Canada–US border to the Mexico-US border at El Paso in Texas. It is the only east-west United States numbered highway that connects Canada with Mexico through the US, making it a key transport route. A 12km section of US 62 where it runs through Oklahoma recently benefited from a much-needed rebuild,
  • Oklahoma highway surface upgrade
    February 2, 2017
    A milling and paving project has provided a necessary surface upgrade for a busy stretch of highway in Oklahoma US Route 62 is an important route and runs 3,597km from the Mexico-US border at El Paso, Texas, to Niagara Falls, New York, on the Canada–US border. A 12km section of the road where it runs through in Oklahoma recently received a rehab. The Oklahoma Department of Transportation (ODOT) project started in Blanchard, Oklahoma, and headed west. This stretch was built in 2000 when ODOT was switc
  • Highway widening project for the US
    April 19, 2018
    A highway widening project in the US state of New Hampshire is being assisted by the use of a gravity-fed asphalt paver. The widening work is being carried out as part of an upgrade for a 32km stretch of I-93, which was started eight years ago. The work is being carried out for the New Hampshire Department of Transportation (NHDOT) on a section of the highway between Exits 1 and 5 from the Massachusetts Stateline to Manchester, NH. According to NHDOT, the project involves widening I-93 from two lanes in
  • Achieving a smooth road surface
    September 28, 2015
    Achieving a smooth road surface has helped a US contractor gain a bonus payment of US$605,000 on a paving job in Montana. A recently renovated 16km section of I-90, starting in Alberton, Mont., which is located on the Western part of the state near the Idaho border, and stretching East, received sterling commendations, beat target IRI scores, and earned the general contractor quality bonuses. The project also won the 2014 MCA Excellence Award for Best Paving Smoothness from the Montana Contractors Associat