Recycling concrete runway saves time, money

Nashville International Airport in the US state of Tennessee has revamped its facilities following extensive upgrades being carried out on its oldest runway in a project worth some US$23 million. The airport authorities realised that to improve both capacity and safety a major improvement of runway 2L-20R was required, with full-depth reconstruction needed to provide the necessary structural strength and working life. Engineering firm Garver Aviation worked on the project to rehabilitate the portion of Runw
February 17, 2012 Read time: 3 mins
A major runway reconstruction at Tennessee International airport has benefited from the use of sophisticated software tools and innovative runway recycling methods
Nashville International Airport in the US state of Tennessee has revamped its facilities following extensive upgrades being carried out on its oldest runway in a project worth some US$23 million. The airport authorities realised that to improve both capacity and safety a major improvement of runway 2L-20R was required, with full-depth reconstruction needed to provide the necessary structural strength and working life.

Engineering firm 2815 Garver Aviation worked on the project to rehabilitate the portion of Runway 2L/20R south of crosswind Runway 13/31 and the project involved building a new concrete runway. Garver provided planning, design, bidding, and construction support and employed some of the latest construction technology, including sophisticated software tools from 4019 Bentley Systems to boost collaboration between the various team members. Using this advanced technology allowed Garver to meet a tight time schedule set by the airport authorities and the 2423 Federal Aviation Administration. Garver used a novel concrete-recycling method to re-use the old runway surface and save the client a considerable sum in materials.

Runway 2L/20R serves as the outbound runway for the airport's Surface Movement Guidance and Control System (SMGCS) and carries a significant portion of the site's cargo operations. However the 35-year old runway was suffering accelerated deterioration due to an alkali-silica reaction. During the project's preliminary stages, Garver approached the Metropolitan Nashville Airport Authority (MNAA) and requested a contract amendment to pursue additional runway testing to determine if the pavement would be suitable for a recycling process to convert old concrete into usable aggregate. After receiving approval, subconsultant KS Ware determined that the Recycled Concrete Aggregate (RCA) method could deliver the required aggregate strength and durability and also be resistant to the alkali-silica reaction.

The runway was closed, and construction crews demolished the pavement with a guillotine breaker. The broken out material was trucked to an on-site crushing and screening plant, pugmilled the blend to moisture condition it, and returned the aggregate to the project as a crushed material to provide a base course for the new runway. Approximately 2,134m of 457-914mm concrete pavement was recycled, including the steel dowel and reinforcement bars.

This process proved to be cost effective as there was no need to haul the concrete waste away from the airport. This was significant as it reduced the cost of aggregate placement from $26.91/ton for virgin material to $4.87/ton for the recycled concrete aggregate. According to Robert Ramsey, Metropolitan Nashville Airport Authority director, "Using the recycled concrete eliminated the need for trucking materials, provided cost savings, and enabled site work to be performed quickly. Garver returned a critical piece of our airfield back to service, and the entire process proved to be very successful." This project also included modifications to every taxiway touching the runway, 10.67m wide asphalt shoulders, full-length in-pavement centreline lights, touchdown zone lights for the 2L approach, drainage work, stormwater management, airfield signs, erosion and sediment control, and pavement markings.

For more information on companies in this article

Related Content

  • Wirtgen SP 1500 dual paver solves four problems at once
    December 8, 2016
    Four job sites, four contractors, four German states, one paving method: Dual-layer concrete paving with the slipform paver SP 1500 from Wirtgen is on the road to success in Germany. Swayed by the numerous economic and technical advantages, more and more planning engineers are opting for this technology when rehabilitating concrete highways.
  • Roadtec machines deliver Alaska runway rebuild
    January 26, 2017
    A challenging airport runway project in Alaska has been carried out with the help of Roadtec construction equipment equipped with Topcon machine control systems. Anchorage-based Knik Construction carried out the work at the airport in Yakutat, located in the southeast corner of Alaska. Bounded by the Gulf of Alaska to the South, mountains to the North, and coastal glaciers to the East and West, Yakutat is remote even for Alaska. There are no roads leading in or out and all commerce and access is by air o
  • Georgia’s on Sandvik’s mind
    February 18, 2013
    Three Sandvik DX800 top-hammer hydraulic drills are said to be playing a key role in developing the new US$92 million Norfolk Southern Intermodal Site within Charlotte Douglas International Airport in the US state of Georgia. The site, in the Georgia town of Austell, encompasses nearly 200 acres of ground, with a granite rock formation lying less than 100m away from a very active runway of the very busy airport. The ground will be turned into an ‘intermodal yard’, meaning that cargo carried there on Norfolk
  • Cost-effective cold mix asphalt recycling
    February 17, 2012
    In Lithuania, cold mix asphalt containing recycled asphalt pavement has been installed in a new base course overlay for a section of the A1, the country's most heavily trafficked motorway.