Recycling concrete runway saves time, money

Nashville International Airport in the US state of Tennessee has revamped its facilities following extensive upgrades being carried out on its oldest runway in a project worth some US$23 million. The airport authorities realised that to improve both capacity and safety a major improvement of runway 2L-20R was required, with full-depth reconstruction needed to provide the necessary structural strength and working life. Engineering firm Garver Aviation worked on the project to rehabilitate the portion of Runw
February 17, 2012 Read time: 3 mins
A major runway reconstruction at Tennessee International airport has benefited from the use of sophisticated software tools and innovative runway recycling methods
Nashville International Airport in the US state of Tennessee has revamped its facilities following extensive upgrades being carried out on its oldest runway in a project worth some US$23 million. The airport authorities realised that to improve both capacity and safety a major improvement of runway 2L-20R was required, with full-depth reconstruction needed to provide the necessary structural strength and working life.

Engineering firm 2815 Garver Aviation worked on the project to rehabilitate the portion of Runway 2L/20R south of crosswind Runway 13/31 and the project involved building a new concrete runway. Garver provided planning, design, bidding, and construction support and employed some of the latest construction technology, including sophisticated software tools from 4019 Bentley Systems to boost collaboration between the various team members. Using this advanced technology allowed Garver to meet a tight time schedule set by the airport authorities and the 2423 Federal Aviation Administration. Garver used a novel concrete-recycling method to re-use the old runway surface and save the client a considerable sum in materials.

Runway 2L/20R serves as the outbound runway for the airport's Surface Movement Guidance and Control System (SMGCS) and carries a significant portion of the site's cargo operations. However the 35-year old runway was suffering accelerated deterioration due to an alkali-silica reaction. During the project's preliminary stages, Garver approached the Metropolitan Nashville Airport Authority (MNAA) and requested a contract amendment to pursue additional runway testing to determine if the pavement would be suitable for a recycling process to convert old concrete into usable aggregate. After receiving approval, subconsultant KS Ware determined that the Recycled Concrete Aggregate (RCA) method could deliver the required aggregate strength and durability and also be resistant to the alkali-silica reaction.

The runway was closed, and construction crews demolished the pavement with a guillotine breaker. The broken out material was trucked to an on-site crushing and screening plant, pugmilled the blend to moisture condition it, and returned the aggregate to the project as a crushed material to provide a base course for the new runway. Approximately 2,134m of 457-914mm concrete pavement was recycled, including the steel dowel and reinforcement bars.

This process proved to be cost effective as there was no need to haul the concrete waste away from the airport. This was significant as it reduced the cost of aggregate placement from $26.91/ton for virgin material to $4.87/ton for the recycled concrete aggregate. According to Robert Ramsey, Metropolitan Nashville Airport Authority director, "Using the recycled concrete eliminated the need for trucking materials, provided cost savings, and enabled site work to be performed quickly. Garver returned a critical piece of our airfield back to service, and the entire process proved to be very successful." This project also included modifications to every taxiway touching the runway, 10.67m wide asphalt shoulders, full-length in-pavement centreline lights, touchdown zone lights for the 2L approach, drainage work, stormwater management, airfield signs, erosion and sediment control, and pavement markings.

For more information on companies in this article

Related Content

  • Lafarge starts Vancouver YVR runway paving
    May 13, 2025
    Lafarge Canada, part of Holcim, is the paving subcontractor for Vancouver Airport’s North Runway Modernisation Programme in British Columbia.
  • Recycled materials
    May 30, 2023
    A road building firm in China is benefiting from the use of a new asphalt plant able to handle a high percentage of recycled asphalt pavement (RAP) in the mix. The firm is operating a Lintec CSM4000HRC asphalt mixing plant that is equipped with a hot recycling system.The plant is being operated by Lu An Highway Industry in China’s Anhui province, providing high-quality asphalt for the S244 regional expressway and other expressway and road maintenance projects.
  • Roadtec changes the game of asphalt paving
    December 20, 2016
    Truly innovative is Roadtec’s Shuttle Buggy material transfer vehicle. John Irvine, President of Roadtec, explains how and why the ‘Buggy’ changed the game of asphalt paving Road paving technology changed dramatically in the 1930s when the American inventor Harry Barber unveiled the very first asphalt paver. Barber was what we today would call a “game-changer”. Innovations like Barber’s don’t come around often. In fact, decades can pass until another breakthrough product pushes the productivity and q
  • Advances in bitumen technology: new applications
    February 16, 2022
    This month, we look at four very different pavement technologies in four very different applications