Serbia upgrading infrastructure

Serbia has managed to reduce the cost of building the Corridor 10 highway by €80 million. These funds will instead be used to pay for upgrades and improvements needed for the second section of the highway project, close to Neradovci.
March 16, 2012 Read time: 2 mins
Serbia has managed to reduce the cost of building the Corridor 10 highway by €80 million. These funds will instead be used to pay for upgrades and improvements needed for the second section of the highway project, close to Neradovci. So far some 180km of the Corridor 10 highway has been built over a 40 month time frame. A further 150km of the highway has still to be built. Work on the Corridor 10 motorway is also being financed by the 1166 European Bank for Reconstruction and Development and the state budget. When Corridor 10 is complete it will provide a valuable transport link for Serbia to its neighbours and also for the region.

Work on the 40km Belgrade ringroad section of the Corridor 10 highway is due to be completed by May 2012, six months before the deadline. The ringroad runs from Batajnica to Bubanj Potok and work is being carried out by the Austrian company 945 Strabag.

The construction work includes building two viaducts, each 1.5km long.

In July 2009, the 2332 World Bank (WB) approved a total of €299 million for construction of the Corridor 10 highway. The WB will allocate €100 million for road maintenance, rehabilitation and road safety improvements in Serbia. Funding will be approved as part of the WB's four year partnership strategy between 2012 and 2015. During the mentioned period, the WB is planning to secure between €462.5-617 million for financing in Serbia. In addition, the Serbian Government has awarded construction of two 25km sections of the Belgrade-Cacak highway project to contractors from Azerbaijan and Russia.

The Obrenovac-Ub to Lajkovac-Ljig section is being handled by a Russian firm, while the Ljig to Cacak stretch is being offered to a firm from Azerbaijan. Some 180km of the highway has been completed.

The tender process for a further 150km of the highway is still underway at present. The Belgrade-Cacak motorway project is estimated at €500 million.

Austrian construction company 3976 PORR is planning to participate in new tenders for construction of the Corridor 10 motorway and the environmental protection projects. The company successfully completed construction of the Ada Ciganlija Bridge in Belgrade, worth €120 million, and construction of a new transportation node worth €70 million. However, Porr will continue with the arbitration process to claim €70 million for cancellation of the concession deal, for the Horgos-Pozega highway.

For more information on companies in this article

Related Content

  • Tenders and financing for Serbian highways
    November 22, 2013
    The Serbian Government is considering a loan from China’s Export-Import Bank, which would pay for the construction of the E-763 highway. The bank looks set to give its approval for the €223 million loan, which would pay for 90% of the construction work for the E-763, or Obrenovac-Ljig, highway. The loan would be approved over a 20 year repayment period and a five year grace period at the fixed rate of 2.5%/year. Meanwhile tendering will open for completion works on Serbia’s Pirot-Dimitrovgrad highway unti
  • Serbia tunnel project due for completion
    June 26, 2012
    Works on Serbia’s Strazevica tunnel is due for completion in May 2012. The tunnel forms part of the Belgrade ring road. Serbia’s government is also planning to finish the construction of a total of 200km of the Corridor 10 motorway, following the completion of the Strazevica–Bubanj and Batajnica–Dobanovci sections. Work on the remaining 130km will commence soon. Meanwhile, work on the Ljig–Preljina section of Corridor 11 is now underway.
  • Serbia: Putevi Srbije to build 2.4km of Corridor 11 access road
    April 14, 2015
    Serbian road contractor Putevi Srbije will build around 2.4km of access roads around the town of Ljig in central Serbia, according the state Ministry of Construction, Transport and Infrastructure. The access roads will be for the Corridor 11 motorway, which is under construction from the Serbian capital Belgrade running southwest into Montenegro, ending at the Adriatic coastal tourist town of Bar. The Belgrade-Bar motorway will be around 280km long and be the main link for a ferry service from the Ita
  • Eastern European highway and tunnel projects
    May 15, 2012
    Serbia’s Corridor 10 project, seen as key to the country’s future economic development, is 20 years behind schedule. With construction delayed and the matter being debated, the Serbian Ministry for Infrastructure, which reported the schedule delay, says the country is working as fast as possible, with 22km being built/year. The corridor will connect the country with its neighbours and provide an important route for through traffic.