Skip to main content

Tenders and financing for Serbian highways

The Serbian Government is considering a loan from China’s Export-Import Bank, which would pay for the construction of the E-763 highway. The bank looks set to give its approval for the €223 million loan, which would pay for 90% of the construction work for the E-763, or Obrenovac-Ljig, highway. The loan would be approved over a 20 year repayment period and a five year grace period at the fixed rate of 2.5%/year. Meanwhile tendering will open for completion works on Serbia’s Pirot-Dimitrovgrad highway unti
November 22, 2013 Read time: 2 mins
The Serbian Government is considering a loan from China’s 1290 Export-Import Bank, which would pay for the construction of the E-763 highway. The bank looks set to give its approval for the €223 million loan, which would pay for 90% of the construction work for the E-763, or Obrenovac-Ljig, highway. The loan would be approved over a 20 year repayment period and a five year grace period at the fixed rate of 2.5%/year.

Meanwhile tendering will open for completion works on Serbia’s Pirot-Dimitrovgrad highway until 9th January 2014. The project was originally to have been carried out by the Austrian company 2859 Alpine. However Alpine hit financial problems and work stopped, so the tender is for the remaining 14.3km of the highway still needing to be completed. The work will be funded by the 1166 European Bank for Reconstruction and Development (EBRD).

At the same time, there is now legal wrangling between the Serbian Government and the liquidation manager for Alpine, Jaksch Schoeller & Riehl. The Serbian company 3235 Koridori Srbije is seeking a repayment of €78 million in damages at the Vienna Trade Court. However Alpine is seeking payments from Serbia. A second review of the case will be carried out shortly for the respective financial demands.

Related Content

  • Work on Serbia’s Corridor 10 highway is on track
    April 3, 2014
    In Serbia work on the Corridor 10 highway looks set to be completed as planned in 2016. Serbian roads company, Koridori Srbije, says that that the Corridor 10 motorway should be completed by the middle of 2016. The World Bank (WB) mission visited building sites on Corridor 10 and said that considerable progress has been made, with an additional 23% of works having been carried out in the last 18 month period. In 2014 alone, 50km of the route will be completed. Work is being carried out on 238 bridges, out o
  • Serbian roads to get Chinese funding
    November 28, 2012
    Talks between the Chinese Development Bank and the Serbian Government could result in €400-€450 million of Chinese funding for Serbian highway projects. The Danube coast and the Corridor 11 projects are among those earmarked for a potential cash boost. Serbia’s Ministry for Transport (MOT) is also in talks with Chinese partners about other highway builds including100km of the Belgrade-Cacak, Belgrade-Obrenovac, Preljina-Ljig and Lajkovac-Ljig routes, as well as the 100km Pojate-Preljina project. China Road
  • Serbia’s pan-European Corridor X is in the slow lane
    October 23, 2017
    It’s been slow progress on Serbia’s Corridor X project. Gordon Feller reports. Back in the early 2000’s, the European Union undertook an ambitious programme to link the main cities of its south-eastern region. This involved connecting five key seaports – the Greek cities of Patras, Igoumenitsa, Piraeus and Thessaloniki as well as Romania’s Black Sea city of Constanta. Initially the plan involved two motorways across Greece. The first was a new 780km route including a branch to Ormenio on Greece’s north-eas
  • Corridor 10 project in Serbia may be delayed
    April 2, 2013
    A series of challenges are now facing the project to construct Serbia’s key Corridor 10 highway. The EU has asked the Serbian Government for details of the priority plan and deadlines for the completion of the Corridor 10 highway. At present three sections of Corridor 10 are at risk, due to delays and financing issues. These are the Ciflik-Pirot stretch, the Bancarevo tunnel and the Vladicin Han section. According to Serbian roads company Koridori Srbije, the construction schedule will be set by the end of