Newly constructed low-noise asphalt surface fails

Questions are being asked over the construction of a new section of the A1 autobahn in Germany. The highway stretch is being scrutinised due to surface failures and lies close to the city of Bremen but has been open for less than three months.
May 15, 2012 Read time: 1 min
Questions are being asked over the construction of a new section of the A1 autobahn in Germany.

The highway stretch is being scrutinised due to surface failures and lies close to the city of Bremen but has been open for less than three months.

The road carries around 70,000 vehicles/day and its construction was intended to reduce congestion between the port cities of Hamburg and Bremen. Numerous potholes are reported to have appeared in the surface of the highway. Given the recent severe weather, failures of older road surfaces are expected but these problems should not occur on links that have been so recently completed.

The investigations will focus on how water penetration into joints could have already caused the freeze-thaw process to break up the running surface or whether other problems such as material segregation or incorrect mix design could have been factors. The low-noise asphalt surface is crumbling at various points along the 73km section recently opened.

Related Content

  • Two new road construction machines for Massenza
    June 24, 2021
    Italian manufacturer Massenza, which produces bitumen emulsion and concrete equipment for road construction markets around the world, has been hard at work over the past two years developing two new machines.
  • Busy bridge in Beijing replaced quickly
    March 31, 2016
    The replacement of a very busy road bridge in China’s capital Beijing has been carried out successfully. Due to the volume of traffic using the bridge during week days, the work had to be carried out quickly so as to minimise traffic disruption. But despite being carried out in the centre of Beijing, the replacement work for the Sanyuan Bridge just took 43 hours from start to completion.
  • Germany plans replacement for A40 Neuenkamp Duisburg Bridge
    March 6, 2018
    Germany’s motorway authority has unveiled plans for an 802m cable stayed replacement bridge taking the A40 over the Rhine River near Duisburg. The state owned authority Deges - Deutsche Einheit Fernstraßenplanungs- und -bau - will oversee the project that includes an eight-lane expansion of the A40, all in the industrial Rhur region.
  • Nuphalt’s novel patching system offers fast and efficient road repairs
    September 2, 2014
    Fast, efficient and long-lasting repairs are claimed for the heating system developed by the Nu-Phalt Group Developed in the UK, the innovative Nu-Phalt pothole patching system equipment is now being widely used by various local authorities for road repairs. But this technology is also being employed internationally, with key sales in parts of Eastern Europe and India.