High performance pavers build high performance track

Work on the new Formula 1 racing circuit in Abu Dhabi is progressing at high speed. Over 6,000 construction personnel are working in the United Arab Emirates (UAE) to complete the new high-speed circuit and its infrastructure. German contractor Bickhardt-Bau is carrying out the paving work, using a fleet of new Vögele pavers and Hamm compaction rollers.
February 29, 2012 Read time: 3 mins
Paving work for the new UAE racetrack has been carried out hot to hot, with two SUPER 1900-2 pavers working together on the straights
Work on the new Formula 1 racing circuit in Abu Dhabi is progressing at high speed. Over 6,000 construction personnel are working in the United Arab Emirates (UAE) to complete the new high-speed circuit and its infrastructure. German contractor 3357 Bickhardt Bau is carrying out the paving work, using a fleet of new 1194 Vögele pavers and 228 Hamm compaction rollers.

The contract has been challenging with 5.5km of paving for the race track, pit lanes, paddocks and emergency roads. As this is a race track and the vehicles using it reach incredibly high speeds, build quality has had to be to the highest possible standards in terms of factors such as structural strength, smoothness and skid resistance. In all, the project in Abu Dhabi has required laying 950,000tonnes of crushed stone for the base course and surfacing 750,000m² with 210,000tonnes of asphalt.

The contractor is using two high-performance SUPER 1900-2 pavers equipped with AB600-2TP2 screeds. The high compaction screeds are proving valuable for laying the different courses to the high standards required. For the base and binder courses, the high compaction exerted by the tamper and twin pressure bars on these screeds has been particularly important. In this configuration, the pavers have delivered pre-compaction of 92% and more.

Contractor Bickhardt Bau met the high requirements in terms of accuracy using the sophisticated Niveltronic Plus control system fitted to the Vögele pavers as this package provides automated grade and slope control. On the racetrack, 20m wide, base and binder courses were paved on most sections and these were installed in four strips of 5m each. When paving the 80mm base course for the straights and wide bends, Bickhardt Bau installed a tensioned wire on the outer side of the first strip. For the adjacent strips, the firm used the slope sensor combined with a multiple sonic sensor tracing the previously paved strip. On the tight bends, a tensioned wire traced by the multiple sonic sensor, was used for all four strips.

The composition of the mix is key to racetrack construction: on a crushed-stone base, 50cm thick and spread by graders, 80mm asphalt base (0/19) was paved. The binder course, laid in a thickness of 40mm, is aggregate with a maximum grain size of 14mm bonded with polymer modified bitumen. For the surface course, a special mix for racing circuits was used, based on aggregate with a grain size distribution of (0/11).

For more information on companies in this article

Related Content

  • Asphalt paver performs well on difficult roads
    February 15, 2012
    Italian paving contractor VARESCO has made good use of its new AP500E paver from Caterpillar Paving on two difficult jobsites. One was a confined site with an abundance of manholes. The other one featured a road with a slope so steep the transport truck trailers were covered to prevent material from spilling out the back. The confined site required paving of an access road leading to a residential area in Merano, a town of 38,000 in northern Italy.
  • Asphalt paving is seeing innovative new technology
    April 4, 2013
    With new machines coming to market, the asphalt paving sector is seeing an array of sophisticated technology now available
  • Compaction in the field
    July 31, 2012
    Special applications require stringent quality control and with compaction machines a key part of the paving process, their contribution can be vital. A high quality finish has helped athletes breaking sporting records on the track at the Shanghai Stadium in China during this year's 2008 Summer Olympic Games. Built in 1997 the stadium has been the venue for numerous major sporting events prior to the Olympics, however its track was showing signs of wear and the local authorities decided that a full refurbis
  • VÖGELE and Hamm race to the finish line at Gardermoen Raceway
    March 28, 2017
    A professional drag race takes only a few seconds. But in these brief moments, everything – including the track surface – must be absolutely perfect. Apart from having excellent grip, the track must also be completely even. So, when Stange Asfalt was rehabilitating the Gardermoen Raceway near Oslo - Norway’s only permanent dragstrip – the company used state-of-the-art equipment supplied by VÖGELE and Hamm. On the dragstrip, the drivers accelerate up to top speeds of more than 500kph within seconds. After