Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Bomag’s president Ralf Junker puts his faith in BIM
    November 8, 2017
    World Highways recently caught up with Ralf Junker, president of BOMAG Group, during the company’s Innovation Days at its headquarters in Germany. David Arminas reports. Ralf Junker hasn’t forgotten his roots. You can put as much machine control as you like on a piece of construction equipment but all that high-technology is for nothing if the build quality isn’t there. Junker knows something about build quality. When he started at BOMAG in 1988, he was in the welding shop, eventually becoming supervisor
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • UK Government’s green light for new Taunton road link
    May 22, 2013
    Work on a new link road will go ahead in Taunton, western England after receiving final approval from Local Transport Minister Norman Baker. The work is needed to improve east-west connections across Taunton and open up access to new development. The overall US$32.07 million (£22.1mn) scheme will see Somerset County Council construct a new road linking Staplegrove Road in the west of the town to Priory Avenue in the east. “This important scheme will help to reduce traffic demand through the town centre and
  • It’s a blast! Road Dryer RD-1200XT
    November 28, 2018
    Traditional pavement drying typically involves the use of jet engine dryers, infrared heat and portable blowers, combined with brooms and manual squeegees. Each method has its limitations along with safety concerns. These include the use of jet fuel, noise, melting pavement, danger from thrown rocks or other objects – not mention slow results. Because of this, traffic is often fully restricted from traveling on roads or runways where drying work is taking place.