Aggregate Industries finishes Leeds project ahead of time

Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning. Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail. The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly
January 24, 2019 Read time: 2 mins
No time to waste: Aggregate Industries worked full tilt 24/7 to finish the Leeds project
Aggregate Industries says that it finished work on a major road improvement scheme in Leeds, UK ahead of schedule thanks to meticulous planning.


Located immediately off the M1 Junction 44, the A639 from Leeds Road to Pontefract Road connects the motorway slip road and a number of local distribution centres, including one for the Royal Mail.

The carriageway required extensive planning and adjustments as well as replacement of ironwork and kerbs. A key requirement was that it needed to be completed quickly and with minimum disruption to nearby businesses and the travelling public.

The 2297 Aggregate Industries contracting team liaised closely with local businesses for three months prior to the start of work onsite. They put together a phased 24-hour working programme that maintained access to affected businesses throughout the duration of the works.

Using this fastidious 24-hour working approach, no time was lost between shift changeovers. During phase 1 of the works, Aggregate Industries laid a 5,855tonnes of asphalt and around 7,500m2 of geotextile in just one weekend. Saturday night alone recorded 3,872tonnes of asphalt laid in 18 hours. This averaged at an 215tonnes every hour during this period.

Aggregate Industries completed their work well ahead of schedule and delivered the project in just 54 hours compared to the 58.5 hours that were originally scheduled.

“To plane out Friday night and inlay 5,855 tonnes of asphalt by Sunday evening is simply unprecedented and we are incredibly proud of what we achieved on this project,” said Paddy Murphy, managing director of contracting services at Aggregate Industries.

For more information on companies in this article

Related Content

  • Installation underway of first UK M4/M5 ‘superspan’ gantries
    July 4, 2012
    The installation is underway of the first superspan gantries on the M4/M5 managed motorway scheme. The existing gantries and infrastructure were successfully removed last month while the new steel gantries were being constructed, fitted-out and tested at a dedicated facility located near junction 17 of the M5, before being delivered to the works site. A total of 33 new overhead gantries, a number of which span 50m and weigh over 30tonnes, will be installed along the new managed motorway section up until T
  • Mini-bridge aids Forth repairs
    July 17, 2012
    An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly A new report to the Forth Estuary Transport Authority (FETA) in Scotland recommends appointing Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009. However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 mill
  • Successful resurfacing at New York's JFK Airport
    May 3, 2012
    A huge logistics operation has been carried out successfully at New York's JFK Airport. One of the busiest runways at one of the world's busiest airports is now open to air traffic again, following a 120 day closure for resurfacing.
  • Dual layer, hot to hot paving at German airport
    August 18, 2015
    An airport in Germany has seen the use of very innovative asphalt paving techniques, with the use of dual-layer, hot-to-hot working. The method was used to meet a very tight schedule for the runway rebuilding work, while also delivering the high quality required. Two InLine Pave trains from Vögele were used at Rostock-Laage Airport to lay a new surface and binder course. The operation was innovative as the process used both hot-to-hot, echelon paving as well as dual layer, hot-on-hot working. Using this