Tensar’s Glasstex makes the grade in UK’s Smart Motorway upgrade

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.
February 27, 2017 Read time: 3 mins
Smart move: Foster Contracting is laying 300,000m2 of Tensar’s Glasstex P100 composite on the M3

A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.

More than 130,000 vehicles use the M3 between Junctions 2 (Thorpe and the M25 motorway) and 4a (Farnborough) every day.

As part of 8100 Highways England’s Smart Motorways programme, the capacity of this congested three-lane section is being increased, with hard shoulders converted to ‘smart’ running lanes.

Construction began on site in January 2015. Asphalt surfacing contractor 2399 Tarmac, working for the principal contractor 1146 Balfour Beatty, is carrying out structural resurfacing of the carriageway as part of the project.

“The road is in poor condition, the result of reflective cracking of the asphalt, due to movement of the underlying layers that are made up of both lean mix concrete and bituminous road base,” says Tarmac project manager Barrie Farquhar. “Repairs were needed to strengthen the road and to prevent further cracking, which could have led to water ingress and further deterioration of the concrete.”

Highways England needed a pavement solution that would reduce initial costs, increase service life, as well as minimise maintenance and future disruption.

Consultant 1397 Aecom had specified asphalt reinforcement in the pavement design. Tarmac, subcontractor Foster Contracting and 340 Tensar International proposed Tensar’s Stress Absorbing Membrane Interlayer (SAMI) Glasstex solution, while supporting the required departure from the standard process.

“The SAMI adds tensile stiffness, increasing pavement strength at low strain and mitigating reflective cracking from both traffic-induced stress and from defects in the underlying pavement structure. It also acts as a moisture barrier,” explains Tensar Highways manager Craig Andrews. “This low-maintenance solution will extend the operating life of the pavement, reducing whole-life costs.”

A total of 300,000m2 of Tensar’s Glasstex P100 composite is being laid by Foster Contracting, on both the northbound and southbound carriageways, along the 26km stretch of road – a total of 52km. This composite of glass yarn grid and paving fabric forms an interlayer between the fractured substrate and the asphalt overlay.

“Glasstex adheres to the underlying pavement structure using a straight run bitumen (160/220 pen) bond coat, with a calibrated spray rate of 1.1kg/m², to activate both stress relief and interlayer barrier functions [as given by BS EN 15381: 2008], with reinforcement provided by the grid,” Andrews says.

“Combined with Tarmac’s Ultilayer polymer-modified binder course, this delivers maximum possible crack resistance and durability.”

An added benefit of installing a SAMI Glasstex solution on motorway projects is speed, Andrews adds. “Work typically has to be carried out at night, which obviously limits the amount of time available. Using Glasstex means the reconstruction depth is far shallower. On the M3 it is just 120-150mm, rather than a minimum 360mm with a standard approach, which obviously saves time and, as a result, construction costs.”

With surfacing work progressing well and half the new gantries installed by the summer, the M3 Smart Motorway project looks to be on target to finish as planned in June 2017.

For more information on companies in this article

Related Content

  • Lindsay Transport’s Road Zipper at Hirschstetten and Stadlau Tunnels
    July 5, 2016
    Lindsay Transportation Solutions recently used the Intertraffic exhibition in Amsterdam to highlight a major deployment of its Road Zipper System in Austria Work is underway in Vienna to rehabilitate two ageing tunnels and the asphalt highway sections that connect them – a major route into and out of the Austrian capital Vienna. Tunnels, like bridges, offer additional challenges for road works. Typically, there is very little additional space and a work zone must be created from active traffic lanes. The
  • Smart vehicle tracking system from Colas and Iknaia
    April 1, 2016
    Colas and wireless systems technology specialist Iknaia have developed a sophisticated system that allows the real-time active management of diversion routes without recourse to ANPR technology. The Airscan package uses anonymous Wi-Fi and Bluetooth signals transmitted by visible devices in passing vehicles. Data is collected by sensors and relayed to variable messaging signs (VMS) which then advise road users in advance of potential delays and allow for strategic checks by maintenance teams. As part of
  • New UK dual carriageway opening
    December 20, 2016
    Drivers in the UK are to benefit from the opening of a new dual carriageway connection. The section of road is a key route for Highways England, improving the connection between junction 19 of the M6 and junction 7 of the M56 motorways. The new A556 Knutsford to Bowdon link road will cut congestion and journey times for drivers in the area. As part of the £192 million project to build the new dual carriageway between, Highways England has remodelled slip roads at Yarwood Heath and Bowdon roundabouts. The
  • Building Egypt's world class Desert Highway
    May 3, 2012
    A huge highway upgrade project will transform the Cairo-Alexandria road link into a world-class connection as Mike Woof reports. The work to upgrade the Desert Highway connecting Egypt's sprawling capital Cairo with its major port Alexandria, is one of the country's largest infrastructure projects for many years. This 220km highway link is being widened and improved to cope with the hugely increased traffic volumes resulting partly from Egypt's fast growing vehicle population. The Egyptian economy is strong