Machine control used for road revamp for Arkansas highway

A historic route in the US state of Arkansas has benefited from the use of machine control during its upgrade The south-west - north-east US Route 67 in Arkansas has long been a significant transport route. This old road follows the natural break between the Ozark Mountains and the Ouachita Mountains. In the 1920s, funding became available for road paving, and the route was designated US Route 67.
June 23, 2015 Read time: 5 mins
Using the latest machine control technology helped boost productivity and quality, while lowering costs for the contractor

A historic route in the US state of Arkansas has benefited from the use of machine control during its upgrade

The south-west - north-east US Route 67 in Arkansas has long been a significant transport route. This old road follows the natural break between the Ozark Mountains and the Ouachita Mountains. In the 1920s, funding became available for road paving, and the route was designated US Route 67.

Over the years, traffic volumes have increased significantly on US Route 67, which has required maintenance, rehabilitation, and in some cases newly developed stretches.

In 2013, the Arkansas State Highway and Transportation Department let a project to build a new section of Route 67 on a new route, which runs roughly from west of Cash north to Walnut Ridge. This is providing a two-lane divided highway, replacing the original single-lane highway.

Weaver-Bailey Contractors, based in El Paso, AR, won the project and became the general contractor on the US$20 million 15.8km section. Weaver-Bailey is a concrete paving specialty contractor that also performs the earthworks and grading prep work necessary for paving. The project commenced in January 2013 and is expected to be completed by the end of 2015.

“This is brand new roadwork being constructed on former farm land,” said Roger Weaver, paving superintendent with Weaver-Bailey Contractors. “It’s a challenge since the fertile soil really holds moisture. The ground is great for planting crops, but not so great for a concrete highway.”

This past winter was mild for the area. Night-time temperatures could be from -6°C, but during the day the temperatures would typically rise above 4°C. According to Weaver, these were temperatures they could work in and pour concrete.

The new concrete highway features two 3.66m wide lanes and a 610mm shoulder on each side. Weaver-Bailey completed the highway with three layers: a cement-stabiliser base, a thin asphalt interlayer, and a surface layer, using a crew of 14.

The 152mm cement stabiliser functions as a sub-base layer reinforcing and protecting the subgrade. The 308,348m2 of cement stabiliser was rough graded with a dozer and finish graded with a motor grader—both equipped with machine control.

“We want to ensure accurate grade and no material waste so we use 342 Topcon 3D-MC2”, Weaver said. “We’ve been using GPS machine control for some time in our dirt work so we’re familiar with its accuracy and production speed, which we’re also seeing on the paving side as well.”

Weaver-Bailey works with both TrenchSafety and Supply, based in North Little Rock, AR, and Topcon to match the technology to the application.

“They’re familiar with the benefits of machine control and have been using systems on their dirt machines for years, so it was natural for Weaver-Bailey to migrate into paving,” said Steven Simon, TrenchSafety and Supply vice president/branch manager for the Memphis and Little Rock locations. “Along with Topcon and 218 GOMACO, we performed the install and training on the GOMACO GHP-2800 slipform paver—they got up to speed quickly.”

Brian Lingobardo, systems manager 3D road construction for Topcon added, “This was a new machine and application for Weaver-Bailey so it was essential that GOMACO and Topcon were united for the start-up and training.”

A significant benefit, according to Weaver, is that with machine control the project neither requires stakes nor the surveyors to place them.

“We save considerable time and surveyor expense during all phases of the project by having the constant of the data points and design within the system,” said Weaver. “It is so much easier not having to worry about running over stakes and then replacing them. A major plus is having no stringlines in the way.”

The 25.4mm layer of asphalt interlayer was placed by a subcontractor. The bond breaker asphalt lift separates the finish overlay concrete from the cement-stabiliser pavement underneath. It is designed to provide support for the overlay.

“We want the finished road surface to be very smooth, that’s why it’s critical that the cement stabiliser and asphalt interlayer surfaces are graded to tight tolerances,” Weaver said. “Then, to ensure we have the smoothest concrete surface, we used Topcon Millimeter GPS technology on our GOMACO slipform paver.”

The company used a four-track GOMACO GHP-2800 slipform paver equipped with a Topcon 3D paving system on the project. The paver features an IDBI in-the-pan dowel bar inserter, paving 7.25m wide, inserting 23 bars across the slab, 300mm apart.

“The machine’s operating system with stringless technology benefited us greatly in lower costs, higher production, and better results,” said Weaver. “We’ve been using 3D paving for the past two years and like that we get real-time navigation with direct access to the design data from our CAD project model. It accommodates radii and superelevations automatically.”

Topcon's Millimeter GPS Paver System controls the lift cylinders independently. The machine operator has access to critical information. The GX-60 control box in the GOMACO paver’s operator compartment features a screen display of machine position on the job, and the sensors being used to control the left and right side of the screed, and current elevation and slope.

A 254mm thick finish surface layer of PCCP (Portland Cement Concrete Pavement) concrete was poured using standard Class A3 concrete. The nearly 32km of paving will require 266,868m2 of PCCP concrete. Other than delays from rain, “the pour,” according to Weaver, “is going smoothly, giving us the smooth road surface we are after.”

For more information on companies in this article

Related Content

  • New concrete surface for Arizona freeway
    November 15, 2013
    In Tucson, Arizona, contractor McNeil brothers is using a two-track GOMACO concrete slipformer on a 3.2km stretch of highway. This project is for the Arizona Department of Transportation (ADOT) and involves widening Interstate 10 to four lanes of traffic in each direction between Ruthrauff Road and Prince Road in Tucson. This new stretch was needed to better handle increasing traffic demands in the city and includes rebuilt entrance and exit ramps to improve access to the city.
  • Australian contractor’s stringless slipforming switch
    April 27, 2015
    An experienced contractor in Australia is benefiting from using stringless controls for slipforming work to boost efficiency. Set up times are shorter using the Topcon technology for stringless paving An Australian contractor is now benefiting from using stringless controls for slipforming work on its Power Curbers machine Statewide Kerbing of Sydney, New South Wales, has been an innovator with different types of slipforming work in Australia. And the firm has taken that one step ahead by using the
  • Efficient concrete overlays
    February 15, 2012
    Concrete overlays have a long history and proven success in the state of Iowa. Mitchell and Worth counties in north central Iowa have led the way. In the past three years, they have put down approximately 241km of 102mm concrete overlay. Concrete Foundations Inc. (CFI), based out of Hiawatha, Iowa, has slipformed almost 80km of the counties' overlays, including 45km this paving season near the town of Osage. CFI has slipformed most of the overlays with its GOMACO two-track GP-2600 paver. This season, the co
  • Machine control technology shortens road contract
    May 28, 2013
    The use of sophisticated machine control technology has helped halve the schedule required for a road contract – Jeff Winke. By using the latest machine control systems on the equipment fleet, a US contractor has managed to halve worker hours, machine time and overall costs. “We chopped 50% off the contract schedule,” said Jim Swenson, licensed professional land surveyor for Oregon Mainline Paving based in McMinnville, Oregon. “The project was completed a year ahead of the two-year schedule,” he explained