Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • New international trade crossing linking Canada and US
    June 9, 2015
    The Detroit River is short, only 45km, and narrow in places, less than 1km. Around a quarter of the annual $658 billion Canada-US trade crosses over the river. That’s $160 billion worth of goods trucked each year between Detroit in the US state of Michigan and the Canadian city of Windsor in the province of Ontario - the Windsor-Detroit Corridor. There are several types of crossings, but the vast majority of commercial traffic must use the 2.3km Ambassador Bridge (see box). A new bridge was initially prop
  • BC awards last Kicking Horse contract
    November 20, 2020
    Phase Four includes 4km of new highway in Canada’s mostly westerly province.
  • Tougher glass bead regulations
    March 16, 2012
    New Jersey has joined Louisiana and North Carolina in with a law limiting the levels of arsenic and lead in glass bead products used for highway safety markings.
  • Gordie Howe Bridge opening date set
    January 15, 2024
    The bridge connecting Detroit in the US state of Michigan and Windsor in the Canadian province of Ontaria will open in September next year.