Skip to main content

Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • Gordie Howe Bridge progresses with community support money pledged
    June 18, 2019
    The Windsor-Detroit Bridge Authority and other agencies involved in the US$4.25 billion Gordie Howe International Bridge have pledged millions of dollars in community support. WDBA, contractor Bridging North America, the US state of Michigan and the federal Canadian government announced the support plan, which involves more than 30 agencies and organisations, according to a report by the Canadian Broadcasting Corporation. The plan includes a $15 million Neighbourhood Infrastructure Strategy for both s
  • Head of San Miguel moots a Philippines bridge project in Boracay
    June 8, 2016
    The president of infrastructure group San Miguel has mooted that a 2km toll bridge be built to connect the small island holiday resort of Boracay with the Larger Panay Island. Boracay - just over 10km2 - is an increasingly popular international tourist destination around 315km south of the Philippine capital Manila and 2km off the northwest tip of Panay in Western Visayas island group. The island is blessed with exceptionally white sand beaches and is administered by the Philippine Tourism Authority and
  • Newfoundland boosts repair spend for 2023-24
    April 24, 2023
    The eastern Canadian province will spend an “unprecedented” US$167 million.
  • Pūhoi-to-Warkworth motorway project
    September 25, 2020
    After a hiatus because of the COVID-19 lockdown, work has restarted on what will be one of New Zealand’s most visually impressive motorways. Andrew Thackwray, senior manager for project delivery for Waka Kotahi, the New Zealand Transport Agency, explains