Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • Ferrovial loses control of Canada’s 407 Express Toll Road
    August 27, 2019
    Ferrovial has lost control of the 407 International highway in Canada, one of the Spanish group's star assets. The Supreme Court in the province of Ontario has ruled in favour of co-shareholder pension fund Canada Pension Plan Investment Board to buy another stake - 10.01% - in the highway. The shares are up for sale by another shareholder, Montreal-based global infrastructure engineering firm SNC-Lavalin. The court denied Ferrovial, which already has the largest shareholding at 43% in the highway, th
  • A virtual virtuous circle
    March 19, 2021
    Virtual sensors will allow a safer driving experience and reduce road maintenance costs. Tactile Mobility’s Eitan Grosbard talks to David Arminas
  • Canadian air
    February 8, 2012
    Compressors from Atlas Copco are proving highly useful in highly diverse applications, on a bridge project and a quarry in Canada. Water ingress over 30 years has damaged a road bridge in Quebec City, Canada, deteriorating the concrete and breaking down the rubber expansion joints at both ends of the 150m long structure. City highway authority, Transportes Quebec, awarded local contracting company Inter-Structures the contract to replace the deteriorated concrete and fit new membrane seals. The bridge, clos
  • A new transportation project for Northern Southeast Asia
    March 2, 2022
    Transport in Northern Southeast Asia is to benefit from a new US$145 million project