Skip to main content

Testing time for Tlicho all-season gravel road in Canadian north

Contractors on the 97km Tlicho all-season gravel road in Canada’s far north are on site despite not having all proper approvals, according to Canadian media.
By David Arminas January 27, 2020 Read time: 2 mins
Opening ceremony for the Tlicho all-season gravel road, August 2019: Whati chief Alfonz Nitsiza, member of the Northwest Territories Assembly Jackson Lafferty and Northwest Territories minister for industry Wally Schumann

The issue concerns several quarries along the route that have not been given the go-ahead from local the Wek'e'zhii Land and Water Board. So far no action has been taken against the  Northwest Territories Department of Infrastructure, lead agency on the project. Discussions are ongoing.

Construction started last autumn on the two-lane road from Highway 3 to Whatì, an isolated town of around 500 mostly indigenous people in central Northwest Territories and about 165km north of the territory capital Yellowknife. The gravel road will replace a seasonal gravel road. Heavy trucks will be able to use the new road which will have a speed limit of 70kph. It will also allow better access to several large mines along its route.

The water licence and land-use permit were issued to the territorial government’s Department of Infrastructure for the public-private partnership contract of around US$316 million.

The Tlicho All-Season Road Project is notable for being the first P3 deal in Canada with an indigenous government holding an equity stake, according to a report by the CBC - Canadian Broadcasting Corporation. The Tlicho Government has a 20% ownership in the project.

Construction is by North Star Infrastructure, a consortium of Kiewit Canada Development and the Tlicho government – an indigenous regional authority, along with Peter Kiewit Sons ULC, Hatch Corporation and Thurber Engineering as design and engineering partners.

Federal government agency Infrastructure Canada is providing 25% of the $165 million construction cost. North Star will operate the route for 25 years after it opens in the winter of 2021 or early 2022. At the end it will be handed to the Northwest Territories government.

Quarrying for the project requires geotechnical analysis to ensure the material to be quarried does not pose a risk of chemicals or heavy metals leaching into the ground.

Other environmental issues have cropped up including food waste left around work camps that might attract wildlife, such as bears, as well as a spill of 15,000 litres of grey water but which was quickly contained. In the northern regions of Canada, the environment is particularly sensitive because of slow decay and recovery rates due to the ground being frozen for much of the long winter.

Related Content

  • Serbia’s pan-European Corridor X is in the slow lane
    October 23, 2017
    It’s been slow progress on Serbia’s Corridor X project. Gordon Feller reports. Back in the early 2000’s, the European Union undertook an ambitious programme to link the main cities of its south-eastern region. This involved connecting five key seaports – the Greek cities of Patras, Igoumenitsa, Piraeus and Thessaloniki as well as Romania’s Black Sea city of Constanta. Initially the plan involved two motorways across Greece. The first was a new 780km route including a branch to Ormenio on Greece’s north-eas
  • Stonehenge Tunnel project faces further questions
    May 22, 2019
    Plans to construct a tunnel link for the A303 route past the famous Stonehenge monument have hit further problems.
  • A free bridge? You’ve got to be kidding.
    February 18, 2015
    Nothing will stop construction of another bridge crossing the Detroit River to ease traffic congestion around North America’s most important economic border. The New International Trade Crossing will be entirely financed and owned by the Canadian government under a public private partnership. It will link the US city of Detroit, in the state of Michigan, with the Canadian city of Windsor in the province of Ontario. The two cities already have the toll road Ambassador Bridge as well as a toll road tunnel and
  • Rwanda to upgrade Mahama camp road
    December 19, 2022
    The successful bidder for project will be responsible for the design and construction of the road from Rusozi to the camp, as well as maintenance for three years.