Storstrøm Bridge JV asks for extension

The original estimated cost was around €280 million for the 4km cable-stay structure when the contract was awarded by the Danish Road Directorate (Vejdirektoratet).
By David Arminas July 13, 2023 Read time: 2 mins
The Storstrøm Bridge will have an electrified two-track railway, a two-lane road and foot and cycle paths (image courtesy Danish Road Directorate / Vejdirektoratet)

Italian consortium Storstrøm Bridge Joint Venture has proposed a 27-month extension and an additional €454 million (US$502 million) for completion of Denmark’s new Storstrøm Bridge.

The original estimated cost was around €280 million for the 4km-long 26m-wide single-support cable-stay structure when the contract was awarded by the Danish Road Directorate (Vejdirektoratet) in 2018. But delays to construction start caused by Covid and other cost increases has gradually pushed up the price of the new structure that run nearby to the exiting Storstrøm Bridge.

The main contractors in the Italian Storstrøm Bridge Joint Venture are Itinera, Grandi Lavori Fincosit and Condotte. The new double-track road and railway bridge includes a central cable-stayed bridge with two spans, 320m long and two access viaducts with 44 spans of 80m, for a total length of nearly 4km. It will have an electrified two-track railway for trains running at 200km/h and a two-lane road with a speed limit of 80km/h. The bridge will also have a foot and cycle paths.

The old bridge, due for demolition when the new one opens, is a 3.2km, a road and railway arch structure opened in 1937 across the Storstrømmen strait between the islands of Falster and Masnedø.

For more information on companies in this article

Related Content

  • Italian JV wins Denmark’s Storstrom Bridge construction deal
    October 27, 2017
    An Italian joint venture has won the construction contract for Denmark’s replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate – Vejdirektoratet - awarded the work to contractors Itinera, Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €280 million for the 26m-wide single-support cable-stay structure. The European Union will subsidise the work to around €15 million.
  • Storstrom Bridge to be Denmark’s third longest
    March 8, 2018
    Form and functionality come together in Denmark’s latest Storstrom Bridge design. David Arminas reports. An Italian joint venture recently won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate - Vejdirektoratet - awarded the work to a joint venture of Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 milli
  • Five consortia line up for Denmark’s new Storstrøm Bridge project
    June 18, 2015
    The Danish government has shortlisted five consortia for construction of a new Storstrøm Bridge to replace an aging structure. The cost of the bridge connecting the Danish islands of Zealand and Falstser amounts to nearly €563 million (US$625.7 million) and the bridge will be financed by the government's Infrastructure Fund. Companies that qualified for the project are a joint venture consisting of Vinci Construction Grand ProjectsSAS, Hochtief Infrastructure GmbH and MT Højgaard; the consortium of St
  • Denmark: construction of Storstrøm Bridge officially gets underway
    September 27, 2018
    Denmark’s Minister of Transport Ole Birk Olesen has turned the sod to officially start construction of the new 4km road and rail Storstrøm Bridge. The €549 million bridge is scheduled to open for road traffic in 2022 and for rail traffic in 2023. The project budget includes the cost for demolition of the existing bridge that opened in 1937. The 24m-wide single-support cable-stayed structure will connect the islands of Zealand to Falster and touch down on the smaller Masnedø Island.