An Italian joint venture has won the construction contract for Denmark’s replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate – Vejdirektoratet - awarded the work to contractors Itinera, Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €280 million for the 26m-wide single-support cable-stay structure. The European Union will subsidise the work to around €15 million.
October 27, 2017 Read time: 2 mins
A single-load bearing pier design was chosen over an earlier proposal for a twin-pier structure

An Italian joint venture has won the construction contract for Denmark’s replacement 4km-long road and rail Storstrom Bridge.

The 2284 Danish Road Directorate – Vejdirektoratet - awarded the work to contractors Itinera, 3481 Condotte and 3869 Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor.

Estimated cost is around €280 million for the 26m-wide single-support cable-stay structure. The 1116 European Union will subsidise the work to around €15 million.

The bridge – to be Denmark’s third longest bridge – will carry a two-lane regional road between a cycle and pedestrian lane and a twin-track railway. It will connect the islands of Zealand to Falster and touch on the smaller Masnedø island. It is an important part of the railway corridor between the Danish capital Copenhagen and Germany. Passage clearage for ships is 24m.

 Vejdirektoratet project director Niels Gottlieb said that the winning joint venture submitted the best project, based on price and quality.

As a central part of the project the winning joint venture has located its production of bridge elements on the small island of Masnedø, in the immediate vicinity of the bridge construction site.
 
A definitive contract will be signed by the end of the year, he said, with construction to start in the autumn of 2018. Before bridge construction starts, there will be extensive preliminary work and harbour alterations on Masnedø.

The bridge is scheduled to be open by 2020 after which the old bridge will be demolished.

Early studies included refurbishment of the existing 1937 bridge but were concluded to be impractical because of its deterioration.

For more information on companies in this article

Related Content

  • Denmark: construction of Storstrøm Bridge officially gets underway
    September 27, 2018
    Denmark’s Minister of Transport Ole Birk Olesen has turned the sod to officially start construction of the new 4km road and rail Storstrøm Bridge. The €549 million bridge is scheduled to open for road traffic in 2022 and for rail traffic in 2023. The project budget includes the cost for demolition of the existing bridge that opened in 1937. The 24m-wide single-support cable-stayed structure will connect the islands of Zealand to Falster and touch down on the smaller Masnedø Island.
  • Storstrom Bridge to be Denmark’s third longest
    March 8, 2018
    Form and functionality come together in Denmark’s latest Storstrom Bridge design. David Arminas reports. An Italian joint venture recently won the construction contract for what will be one of Denmark’s longest bridges, the replacement 4km-long road and rail Storstrom Bridge. The Danish Road Directorate - Vejdirektoratet - awarded the work to a joint venture of Condotte and Grandi Lavori Fincosit along with bridge design consultant Seteco Ingegneria as a subcontractor. Estimated cost is around €550 milli
  • A rough ride for Denmark’s National Road Directorate
    November 1, 2019
    Denmark’s National Audit Office has criticised the Danish National Road Directorate for consistently miscalculating the level of investment required for road projects. The Road Directorate – Vejdirektoratet - used 33% less than budgeted for road projects from 2007-2017. The audit office said that "budget calculations by the transport ministry, including the Road Directorate, have not been accurate enough". Jens Holmboe, head of the Road Directorate, rejected the criticism, saying that the Audit Office
  • Storstrøm Bridge JV asks for extension
    July 13, 2023
    The original estimated cost was around €280 million for the 4km cable-stay structure when the contract was awarded by the Danish Road Directorate (Vejdirektoratet).