Piers completed for Morandi Bridge replacement project

The last of the 18 elliptical 40m-tall piers have been finished.
By David Arminas February 20, 2020 Read time: 2 mins
In total, 19 spans will eventually cradle a continuous steel deck (photo courtesy Salini Impregilo/PerGenova)

PerGenova, the joint-venture constructing the new Genoa Bridge, recently completed the last of the 18 elliptical piers – 40m-tall giants of reinforced concrete.

PerGenova – consisting of Salini Impregilo and Fincantieri – said that it reached the milestone in record time. At the moment, 10 of the 94m-long spans of the deck that will rest on the piers have been installed. In total, 19 spans will eventually cradle a continuous steel deck.

The spans needed to be raised more than 40m into the air and placed atop the piers. Also raised were 14 sidings that resemble wings along the side of the bridge, as well as fittings such as the sections that will facilitate the pouring of concrete. In light of the span’s weight, cranes were not used. Instead, strand jacks were brought it and used cables to hoist the span into place at a speed of 5m per hour.

The bridge replacement work follows the collapse of the old Morandi Bridge in 2018, causing fatalities. The new bridge also represents Progetto Italia, led by Salini Impregilo. The vision is for a new way of building complex infrastructure in Italy where private companies and public institutions come together to develop projects on time and to budget. The goal is to unblock stalled projects and to create innovative ways of working, according to Salini Impregilo.

“This [new bridge] is a unique project from a number of vantage points: there is the innovation and sustainability aspect, the speed at which the bridge is being built, the close public interest and the pressure that comes with it, the attention to quality and safety and, obviously, the very reason for the bridge to come into existence,” said Pietro Salini, chief executive of Salini Impregilo.

The project has up to 600 people working on site daily and more than 1,000 when including the supply chain. Progress can be followed in real time thanks to live streaming at the website www.pergenova.com which gets a round-the-clock feed from eight webcams.

For more information on companies in this article

Related Content

  • Doka feels the heat in Qatar orbital highway project
    September 19, 2019
    The FIFA World Cup 2022 in Qatar is getting closer so completing major infrastructure projects on time has been a priority for the government. The Gulf state is also in the midst of its Qatar National Vision 2030, launched in 2008 with the aim to "transform Qatar into an advanced society capable of achieving sustainable development" by 2030. Improving infrastructure will help the country of just under 3 million people attain greater social and economic levels, according to the government. Finishing critic
  • Crushing and screening for producing and re-using
    July 23, 2012
    The recycling and minerals extraction markets now share technologies, Mike Woof reports Not surprisingly, the Steinexpo quarrying event in Germany was a key launch venue for new crushing and screening technologies, as well as associated quarrying technology. Crushing and screening equipment firms from a wide range of European countries including Austria, the Czech Republic, Germany, Ireland, Italy, Sweden, Switzerland and the UK were present at the exhibition. However it was noticeable how closely the miner
  • Mallatite and TRT Lighting brightens up Scotland’s Erskine Bridge
    December 15, 2017
    Mallatite has supplied aluminium lighting columns and LED road lanterns as part of the Erskine Bridge Lighting and Electrical Refurbishment Project for Transport Scotland. The project is set to enhance night-time driving visibility and reduce energy consumption by up to 80% through the use of dimming. The A898 Erskine Bridge is a 15-span cable-stayed box girder bridge in west central Scotland that opened to traffic in 1971. The longest span is 305m. Around 42,000 vehicles use it daily to cross the River
  • Meva’s Mammut 350 formwork makes the difference for Neckar viaduct
    April 19, 2018
    Formwork specialist Meva is helping replace the longest motorway bridge, the Neckar River viaduct in Germany’s south-west state Baden-Wuerttemberg Work on the 1.3km Neckar viaduct, part of the A6 motorway at Heilbronn, should be finished by 2022. It is part of the A6 expansion project between the Weinberger junction and Wiesloch/Rauenberg. The project is officially the new Neckar viaduct BAB 6 at Heilbronn. Federal Motorway 6, the A6, is also known as the BAB 6. The 477km motorway starts at the French b