Meva’s Mammut 350 formwork makes the difference for Neckar viaduct

Formwork specialist Meva is helping replace the longest motorway bridge, the Neckar River viaduct in Germany’s south-west state Baden-Wuerttemberg Work on the 1.3km Neckar viaduct, part of the A6 motorway at Heilbronn, should be finished by 2022. It is part of the A6 expansion project between the Weinberger junction and Wiesloch/Rauenberg. The project is officially the new Neckar viaduct BAB 6 at Heilbronn. Federal Motorway 6, the A6, is also known as the BAB 6. The 477km motorway starts at the French b
April 19, 2018 Read time: 4 mins
Piers parallel to the old bridge are being built using the KLK 230 climbing platform, the Space shoring tower and Mammut formwork
Formwork specialist 3209 Meva is helping replace the longest motorway bridge, the Neckar River viaduct in Germany’s south-west state Baden-Wuerttemberg


Work on the 1.3km Neckar viaduct, part of the A6 motorway at Heilbronn, should be finished by 2022. It is part of the A6 expansion project between the Weinberger junction and Wiesloch/Rauenberg.

The project is officially the new Neckar viaduct BAB 6 at Heilbronn. Federal Motorway 6, the A6, is also known as the BAB 6. The 477km motorway starts at the French border near Saarbrücken and ends at the Czech border near Waidhaus. It then continues through the Czech republic to the capital Prague. Internationally it is known as Via Carolina.

Around US$21 million was spent on renovating the structure only in 2003 but it has been struggling to handle 100,000 vehicles a day. The extension of the 25km section of motorway for an estimated €1.3 billion was announced at the start of 2017. It was immediately clear that the greatest challenge would be construction of the new six-lane bridge over the Neckar River.

ViA6West, the public-private partnership is working with partners 981 Hochtief PPP Solutions, DIF and BUNTe. ViA6West is responsible for the planning and construction of the bridge as well as maintenance until 2046. In actual fact, two bridges will be created over the Neckar valley: a temporary parallel construction for the ongoing traffic and, after the old bridge has been dismantled, the new bridge.

ViA6West is now constructing the temporary bridge next to the old 1960s bridge in two steps. The first is building a foreland bridge with launching girder and the second is constructing the section over the Neckar using the incremental launching method.

The two sections will meet and be connected shortly before Neckar island. The entire superstructure with the travel lanes and the noise barriers is already complete. Subsequently, the old bridge will be demolished and the final foundations and piers erected.

The highlight of the project is then planned for 2022 - the lateral displacement of the two bridge sections by up to 20m onto the end piers and completion of the structure. For this, 40 hydraulic cylinders will be operated via a computer¬ and camera-controlled system to position the bridge sections to the nearest millimetre. The task will take only a few days and the bridge sections and connections will be completed. A completion deadline is set in concrete - the National Garden Show in Heilbronn, which opens its doors on April 17, 2019. Special formwork when made of wood are designed to be used only once. That the concrete bridge piers and foundations are only temporary structures which are dismantled when the actual main bridge is complete is the exception rather than the rule.


“Building a bridge of this size parallel to the old bridge and then moving it laterally into position is literally a mammoth task,” said Andreas Scherzl, a Munich-based project supervisor. “Foundations for the abutments and the bridge piers are being poured using Meva’s Mammut 350 formwork system, as are the bridge piers themselves.

“The KLK 230 climbing platform and the Space shoring tower ensure that formwork can be erected safely. The launching beams on the piers of the temporary bridge also play a key role to ensure that the entire construction can be manoeuvred laterally into its final position after completion of the superstructure complete with travel lanes and noise barriers,” explained Scherzl.

Meva’s special design department was required for work on round pier columns and the pier heads in the area of the steel reinforced concrete bridge directly above the Neckar River. Alexander Schmid, who is supervising the work, said a 3D programme was used to get the precise bending and twisting in the four formwork panels. At the customer's request the formwork panel had to have a wooden surface.

For more information on companies in this article

Related Content

  • A6 project between Weinsberg and Wiesloch/Rauenberg set to start
    January 26, 2017
    Work will soon start on the €1.3 billion project to widen a stretch of the A6 motorway, one of Germany’s most congested highways. Both sides of the motorway between the Weinsberg and Wiesloch/Rauenberg junctions will be expanded. On 25 km of the section being expanded under the project – altogether 47.1 km – the number of lanes will be increased from four to six. The project also encompasses the construction of the 1.3km-long Neckartal Bridge. Preparatory work for the public-private partnership has
  • Germany's advanced bridge construction
    February 24, 2012
    The A98 single-lane motorway in Germany is being extended by a second pair of lanes. Work began in 2007 and required building a second bridge at Rheinfelden in the south-west of the country, parallel to the existing bridge, and identical in design and construction.
  • Substantial motorway expansion projects planned in Bavaria
    February 2, 2017
    The budget for Germany’s Motorway Directorate for Northern Bavaria will remain at around €520 million for 2017, according to media reports. For many years the budget for the Autobahndirektion Nordbayern (ADNB) was pegged between €320-380 million. This changed last year when it was boosted to €520 million, noted the newspaper Süddeutsche Zeitung. Substantial work is planned on the A3 and A6 motorways and on bridges. The 94km on the A3 between Aschaffenburg and Würzburg will be widened to six lanes by 2
  • Winning formula for formwork
    July 19, 2012
    An unusual application of formwork took place recently in France, while formwork using one particular engineering construction kit was used for the first time in Poland. Guy Woodford reports An 80m long wild game underpass is an innovative feature of the Route Nationale 88 (RN 88) expansion in south-west France. For construction of the arched underpass tunnel, a PERI tunnel formwork carriage using VARIOKIT engineering construction kit was used. Thanks to the equipment’s easy handling, along with pre-assembl