Permanent Fehmarnbelt element factory?

Sund & Bælt has completed an environmental assessment of the tunnel element factory for the 18km Fehmarnbelt project between Denmark’s Lolland and Germany’s Fehmarn islands.
By David Arminas July 7, 2023 Read time: 2 mins
The tunnel element factory on Lolland island could be around for many years after the Fehmarnbelt project is finished (image courtesy Fehmarn/ Sund & Bælt)

Sund & Bælt has completed the environmental impact assessment of the tunnel element factory east of Rødbyhavn on Denmark’s Lolland island in the Baltic Sea.

The assessment by the Danish infrastructure company will form the basis for a political decision on whether to preserve the tunnel element plant where tunnel sections will be fabricated for the 18km Fehmarnbelt immersed tunnel between Lolland and the German island of Fehmarn. The sections will be floated out form the factory to be positioned and lowered into place on the seabed.

Originally, the element plant at Rødbyhavn was to be temporary and dismantled after the elements had been made. However, Denmark’s Infrastructure Plan 2035 set out a proposal to consider the factory being made permanent as a base for future infrastructure work in the area and region in general.

The factory complex – still under construction – will include a protected seaport, access roads, supply chain facilities and office-administrative buildings. Sund & Bælt noted that there are many economic and environmental advantages for making the site permanent, not least that it will preserve jobs.

The factory could manufacture other elements for future public mega-infrastructure projects require will  large scale production and shipping facilities. It could also help produce and ship elements for the large expansion of wind energy farms that is essential for Denmark’s ambition of climate neutrality by 2050.

Meanwhile, Femern – wholly owned by Sund & Bælt and responsible for the Fehmarnbelt project – has launched a website that can assist the many cargo ships calling at the work harbours of the Fehmarnbelt project, one in Denmark and the other in Germany. The new harbour website include requirements for port calls, port layout and information about the tunnel construction and shipping traffic in the Fehmarnbelt.

The website will later include weather information and a webcam, allowing commercial vessels to orient themselves before arrival. The Danish work harbour is in operation and receives on average one cargo ship every three days.

Femern is a subsidiary of Sund & Bælt Holdings, which is 100 per cent owned by the Danish Ministry of Transport. Sund & Bælt Holding is also the parent company of Storebælt, which operates the Great Belt Fixed Link and Øresund, which operates the Øresund Fixed Link.

For more information on companies in this article

Related Content

  • Further delays expected for the Fehmarn Belt Fixed Link
    August 26, 2015
    Further delays to the planned Fehmarn Belt Fixed Link between Germany and Denmark appear likely because of objections to the project during the planning stages, Danish media reported. Government authorities in the German state of Schleswig-Holstein indicated that permission for the project, which focusses on a 17km immersed road and rail tunnel, will probably be given in 2017, and not next year as previously believed. German authorities have received about 3,100 objections to the project that has rise
  • Consortia line up for Denmark’s Storstrom Bridge project
    February 12, 2015
    Samsung, Daewoo, Hyundai, Acciona, Ed Züblin, MT Højgaard and Per Aarsleff are among the bidders to build a bridge connecting the Danish islands of Zealand and Falstser. The Danish Road Directorate expects to choose five pre-qualified consortia for the Storstrom Bridge project in May and the bids for the project are scheduled to be submitted by April 2016. The new bridge, likely to cost around €565 million including the cost of demolishing the old bridge it will replace, is expected to open by 2021, a
  • Challenges mount for the Fehmarn Belt Fixed Link project
    December 15, 2016
    The Fehmarn Belt Fixed Link between Danish and German islands faces ongoing delays that are pushing a construction start past this year and well into 2018. A meeting in mid-December between Danish traffic minister Ole Birk Olesen and his German counterpart Reinhard Meyer for the neighbouring German state of Schleswig-Holstein, highlighted mounting opposition against the €7 billion or more project. During the meeting, Meyer stressed that the Schleswig-Holstein government remains determined to implement
  • Ferry operators sink the financing plan for Fehmarn Belt link
    December 17, 2018
    The Court of Justice of the European Union has said Denmark’s state grant aid to the proposed Fehmarn Belt link is illegal under EU rules. The court noted that the European Commission approved the Fehmarn project’s financing – total cost likely around the €8.7 billion - in July 2015 without a formal procedure. Denmark is completely responsible for financing the project that will replace a ferry service. Part of the funds were to come through the European Union and its Connecting Europe Facility for tr