Further delays expected for the Fehmarn Belt Fixed Link

Further delays to the planned Fehmarn Belt Fixed Link between Germany and Denmark appear likely because of objections to the project during the planning stages, Danish media reported. Government authorities in the German state of Schleswig-Holstein indicated that permission for the project, which focusses on a 17km immersed road and rail tunnel, will probably be given in 2017, and not next year as previously believed. German authorities have received about 3,100 objections to the project that has rise
August 26, 2015 Read time: 2 mins
Further delays to the planned Fehmarn Belt Fixed Link between Germany and Denmark appear likely because of objections to the project during the planning stages, Danish media reported.

Government authorities in the German state of Schleswig-Holstein indicated that permission for the project, which focusses on a 17km immersed road and rail tunnel, will probably be given in 2017, and not next year as previously believed.

German authorities have received about 3,100 objections to the project that has risen in cost to around €8.6 billion.

Reinhard Meyer, minister of economic affairs, transport and technology in Schleswig-Holstein, said that German environmental organisations will likely bring the issue before the court, which will hamper the project’s final approval.

The completion of the project might therefore be delayed from 2021 to 2027.

The Fehmarn Belt Fixed Link will connect the German island of Fehmarn with the Danish island of Lolland. The 17km tunnel, including two railway tunnels, two motorway tunnels and an emergency tunnel, will cross the Fehmarn Belt, or Fehmarn Strait, in the Baltic Sea.

Earlier reports have suggested that Denmark alone is likely to foot the project’s bill for the tunnel project while Germany will pay for only access roads and other connections on its territory.

World Highways reported in February that the Danish government was talking to contractors over the latest rise, a jump of €1.2 billion, in cost estimates for entire project. Contractors estimated an extra €295.5 million will be needed. This is in addition to a statement last November by the contracting company 4782 Femern saying that costs had risen nearly by €900 million.

For more information on companies in this article

Related Content

  • Denmark set to appoint preferred bidder for Fehmarnbelt link
    March 14, 2016
    The Danish political parties behind the Fehmarnbelt link have mandated Femern A/S to appoint preferred bidders for the main tunnel work in order to enter into conditional contracts no later than mid-May. Femern A/S is the Danish government-owned company managing the Fehmarn Belt immersed tunnel project between Denmark and Germany. The project was approved by the Danish parliament in April last year. It is supposed to be built, owned - apart from the German land works - and operated by Femern A/S, a su
  • New study suggests Fehmarn Belt payback close to 50 years
    October 9, 2015
    A study by Danish consultant Hans Schjær-Jacobsen has shown that the payback period for the proposed Fehmarn Belt Fixed Link tunnel project between Denmark and Germany will be close to 50 years. This is a decade longer than estimated by the developers of the project which focusses on a 17km immersed tunnel, the study noted. The Fehmarn Belt Fixed Link will connect the German island of Fehmarn with the Danish island of Lolland. The 17km tunnel, including two railway tunnels, two motorway tunnels and an
  • German government to adhere to Fehmarn Belt tunnel plans
    April 30, 2015
    Germany is to adhere to plans for a tunnel between Fehmarn, Germany, and Lolland, Denmark despite criticism over the cost and a delayed schedule. Denmark alone is likely to foot the €7.4 billion bill for the prestigious Fehmarn Belt Fixed Link immersed tunnel while Germany will pay for only access roads and other connections on its territory. Angela Merkel, Chancellor of Germany, said her government and transport authorities will respond to more than 3,000 objections over the construction of the tunne
  • Fehmarn Belt Fixed Link could open by 2025 at earliest
    November 27, 2015
    The ambitious Fehmarn Belt Fixed Link, connecting Denmark and Germany, will open in 2025 at the earliest, according to the Danish finance ministry. Femern A/S, the Danish government-owned company managing the project, confirmed the note from the government. It also said the ministry still has financial concerns over the deal to build an immersed tunnel connecting the towns of Rødby in Denmark’s southern Zealand with Puttgarden in northern Germany. Of particular is the time for a construction company t