Metrostav Norge's Faroe tunnel on target

Metrostav Norge won the contract to connect the villages of Fámjin and Ørðavík on Suðuroy Island, part of the Faroes, in 2022.
By David Arminas December 18, 2023 Read time: 2 mins
Every tunnel helps: around 80% of the Faroes population is connected by tunnels (image © Niels Melander/Dreamstime)

Work continues by the Czech construction firm Metrostav on a 1.2km tunnel in the Danish Faroe Islands.

The Metrostav Group, through its subsidiary Metrostav Norge, won the contract to connect the villages of Fámjin and Ørðavík in the autumn of 2022. Less than 90 people live in the area which is on Suðuroy Island, one of  in the Faroes island group.

The tunnel is being built using the Norwegian drill-and-blast tunnelling method. Around 220 of the company's employees are on site. According to the company, the deal is worth around €8.8 million. The tunnel is being excavated from a portal located above the village of Ørðavík. Included in the work of Metrostav Norge is grouting and the installation of around 9,000m² water and frost insulation. Around 4,275m³ of shotcrete will have been used upon completion.

The main client is Landsverk, the Faroes highways agency responsible for building, operating and maintain the country’s highway infrastructure.

The Faroe island group in the North Sea is around 320km north of the UK and about halfway between Norway and Iceland. The country is an autonomous  self-governing region of Denmark and legislates and governs independently in a wide range of areas. The country is rugged and has a subpolar oceanic climate - windy, wet, cloudy and cool. Temperatures are moderated by the Gulf Stream, averaging above freezing throughout the year.

Road tunnels – there are no rail services in the island group – are an important part of the transport infrastructure. Around 80% of the population is connected by tunnels through the mountains and between the islands, bridges and causeways that link together the three largest islands and three other islands to the northeast. While the other two large islands to the south, Sandoy and Suðuroy, are connected to the main area with ferries, the small islands Koltur and Stóra Dímun have no ferry connection, only a helicopter service

For more information on companies in this article

Related Content

  • Polish tunnel project being planned
    January 21, 2019
    Construction work on the planned tunnel for the Polish islands of Uznam and Wolin will commence in 2021. The islands lie on Poland’s Baltic Coast and this €184 million tunnel project is intended to improve transport connections in the area. The ferries used at present are ageing and are no longer able to cope adequately with the number of vehicles using the crossing. Up to 11,000 vehicles/day make the crossing during peak summer months, with around 2 million vehicles/year making the trip by ferry at present
  • Croatia’s Peljesac Bridge progressing
    June 11, 2020
    China Road and Bridge Corporation is working through the pandemic period.
  • New Zealand’s Waterview project is moving closer to completion
    December 13, 2016
    New Zealand’s biggest road project is less than a year away from completion, and a lot of progress has been made since World Highways last looked at the project two years ago - Mary Searle Bell reports New Zealand’s Waterview project is moving closer to completion and will be the largest road project in the country. The NZ$2 billion Western Ring Route will see the creation of an alternative motorway to State Highway 1, which runs through the centre of Auckland. The 47km-long motorway will allow a large p
  • COWI wins Massey Tunnel design contract
    February 18, 2022
    COWI will develop an eight-lane immersed tunnel for the George Massey Crossing Project near Vancouver, Canada.