Cost of D1 section Hubova-Ivachnova rises 40%

In Slovakia, the 15km Ružomberok bypass, including the 3.6km Čebrať Tunnel, is now €93 million more expensive than nine years ago.
By David Arminas August 3, 2023 Read time: 2 mins
The Ružomberok bypass project includes the Čebrať Tunnel (image courtesy Slovak National Road Company/NDS)

The cost of the Liptov section of the D1 Hubova-Ivachnova motorway in Slovakia has risen by around 40% to €320 million, according to national media.

The 15km Ružomberok bypass, including the 3.6km Čebrať Tunnel, is now €93 million more expensive than it was nine years ago, the national motorway company NDS is reporting. The D1 Hubova-Ivachnova motorway section should be completed in 2024 compared to the previously planned 2017. The delay was caused by the land slide near the western part of the Čebrať Tunnel.

Earlier this summer, NDS said construction of the D1 between Lietavska Lucka and Dubna Skala in northern Slovakia, which includes the Višňové Tunnel, will be completed within two years.

Meanwhile, Slovakia's Transport Ministry is planning to use funds from the European Connecting Europe Facility programme for preparation of the remaining sections of the D1 motorway. This includes the stretch from Kosice to the border with Ukraine and the R4 expressway from Presov to the Polish border.

The ministry and the NDS will also seek to cover around half of the cost of the northern bypass of Presov's second phase. Slovakia is interested in getting a grant of over €178 million from the Connecting Facility for construction of the second part of the Presov bypass and the remaining R4 sections within the Via Carpatia Corridor.

For more information on companies in this article

Related Content

  • Slovakia tunnel sections underway but some delays
    January 23, 2018
    The route for new tunnel links for Slovakia’s D1 highway has been agreed. New tunnels now look set to be built on the 13.5km stretch between Turany and Hubova section of the D1 highway. This plan calls for the construction of the Korbelka and Havran tunnels at an estimated cost of €900 million. Building these two links would bypass the Lower Fatra mountain range, with the Korbelka Tunnel measuring 5.9km and the Havran Tunnel measuring 2.9km long. The Slovak Environment Ministry rejected an appeal against th
  • Višňové Tunnel delays continue
    June 21, 2022
    What will be Slovakia’s longest tunnel at 7.5km is facing more technical issues, according to the contractor Skanska.
  • Slovakia’s D1 highway project underway
    August 11, 2022
    Work on Slovakia’s D1 highway project is underway.
  • Restart for Slovakia’s Čebrať tunnel and Hubova-to-Ivachnova D1 section
    December 13, 2017
    Work will restart on the 15.2km D1 bypass around the Slovakian town of Ružomberok after the government and contractors amended the contract. The consortium of OHL ZS and Vahostav-SK and the National Highway Company (NDS) recently signed and addendum to the contract that includes an extension of section’s Čebrať tunnel by1.6km to 3.6km and shortening of the road by around 300m. Because of continuing geological concern, NDS had earlier decided to reroute the road and the tunnel. As a result, the cost of the