Colombia: more money for Toyo Tunnel Project

The Toyo Tunnel Project – the Guillermo Gaviria Echeverri Tunnel Project - covers 18.3km including new roads and is under construction by Consorcio Antioquia al Mar.
By David Arminas April 4, 2024 Read time: 2 mins
The 9.7km-long Toyo Tunnel is the longest in Colombia and running deepest at 900m (image courtesy Gobernacion de Antioquia/Government of Antioquia)

The Colombian government has committed nearly US$144 million to complete the Toyo Tunnel Project in the northwest department of Antioquia.

With a population of around six million, Antioquia is one of the 32 national departments and is located in the central northwest part of Colombia with a narrow section that borders the Caribbean Sea. Most of its territory is mountainous much of which is part of the Andes mountain range.

The Toyo Tunnel Project – also called the Guillermo Gaviria Echeverri Tunnel Project- covers 18.3km connecting the municipalities of Cañasgordas and Giraldo. It includes bridges and the 9.7km-long Toyo Tunnel, the longest in Colombia and running deepest at 900m. It is also is one of many in Colombia’s “fourth-generation (4G) highway network” projects to improve connections nationally.

The Consorcio Antioquia al Mar, a consortium, was awarded the 10-year construction contract in 2015, according to BN Americas, a business intelligence platform that provides information and data solutions to project owners, contractors, suppliers and financial services firms. Consorcio Antioquia al Mar consists of infrastructure contractors Colombiana de Infraestructuras, Carlos Alberto Solarte and CASS Constructores as well as tunnelling civil engineering specialist Estyma Estudios y Manejos

BN Americas  also notes that the agreement between the companies gives Colombiana de Infraestructuras, a subsidiary of Spanish company FCC, 40% ownership and a 20% ownership each for Carlos Alberto Solarte, Estyma Estudios y Manejos and CASS Constructores.

Engineering consultancy WSP worked on final studies and designs in Phase III for Section No. 1 for the consortium. Its work included a transportation study, a soil study for the design of bridge foundations and other retaining structures, a slope stability and stabilisation study, geotechnical study and pavement design, hydraulics analysis and tunnel study and designs.

The consortium also worked with Swedish equipment maker Epiroc for drilling and ventilation strategies. Epiroc's Boomer XE3C and Boomer E2C jumbos with ABC Total Navigation systems have excavated around 1.4 million cubic meters of soil.

For more information on companies in this article

Related Content

  • Colombia: two proposals to build Santana-Mocoa-Neiva motorway
    May 7, 2015
    The Colombian Vice President, German Vargas Lleras, has announced that two proposals have been received to build the Santana-Mocoa-Neiva motorway. This road has a budget of US$627.22 million is one of the nine initiatives the National Infrastructure Agency (ANI) has included in the second wave of 4G motorway projects. The two companies interested in carrying out the work are Concesionaria Vias del Desarrollo 4 and Infraestructura Vial para Colombia. Concesionaria Vias del Desarrollo 4 consists of C
  • Colombia’s massive roads programme is seeing delays
    March 19, 2024
    Colombia’s massive road expansion programme is seeing delays.
  • Consortium Via al Puerto to finish Colombia’s Buga-Buevantura road
    May 24, 2016
    Colombia’s National Infrastructure Agency (ANI) has approved Consorcio Estructura Plural Via al Puerto to build the remaining 26.5km of the Buga-Buenaventura dual carriageway. Construction costs will be just under US$358 million with another $645 million likely needed to maintain and operate the public-private partnership road for 30 years. Works include construction of two tunnels, 12 bridges, 7.5km of cycle lanes, as well as maintenance of 111km of the main road, according to a report by El Pais new
  • Colombia tunnel construction contract commencing
    February 5, 2018
    Driving work has commenced for Colombia’s Toro Tunnel project. The tunnel will measure 9.8km long and is located in Colombia’s Antioquia Department, with the completion expected in 2022. The project is costing US$650.5 million and the link is intended to provide a link between the Autopista al Mar 1 and Autopista al Mar 2 highways. When complete the tunnel will also cut the travel time between Medellin and Uraba to four hours.