Breakthrough for Slovenian Karavanke Tunnel

The existing tunnel Karavanke Tunnel tube between Austria and Slovenia opened in 1991.
By David Arminas April 2, 2024 Read time: 2 mins
The Slovenian stretch of the second tube alongside the original tube for the Karavanke Tunnel is around 3.5km, while Austria has had to excavate 4.5km (image courtesy Asfinag/DARS)

After three and a half years of excavation, Slovenia has broken through to the Austrian side of the second tube for the 7.9km-long Karavanke tunnel.

It was two years ago that boring on the Austrian side reached the border point with Slovenia, according to Asfinag, Austria’s government-owned company that manages the country’s highways.

The Slovenian stretch of the second tube is around 3.5km while Austria has had to excavate 4.5km.

Turkish tunnelling contractor Cengiz has done the excavation work on the Slovenian side under a contract signed with the Slovenian state-owned motorway company DARS for the €120 million project at the end of January 2020. The European Investment Bank, EIB, soon after lent the project €90 million.

This new tube, alongside the existing one that opened in 1991, should double the capacity of road transport between Villach, Austria, and Jesenice in Slovenia.

Construction of the second tube between the two countries started in August 2020. Delays on the Slovenian side have been attributed to challenging geological conditions, according to DARS.

Slovenia’s infrastructure minister Alenka Bratušek said he anticipates the second tube to open to traffic in 2025. However, after the new tune opens, work will start on renovating the original tube that is expected to be finished in late 2028.

Construction of the original tunnel began in 1986 to connect the Austrian Karawanken Autobahn , the A11, from Villach with the A2 motorway leading to Kranj and Ljubljana in Slovenia. The opening led to fewer vehicles using the historic Loibl/Ljubelj and Wurzen/Korensko sedlo mountain passes.

Early on in the new project, ASFINAG selected to use BIM, Building Information Modeling, for all relevant structural data, compiling a 3D-model as the project progressed.

For more information on companies in this article

Related Content

  • Strabag to upgrade Austria’s A10 Oswaldibergtunnel
    July 13, 2015
    Austrian construction group Strabag will modernise the A10 Oswaldibergtunnel for Asfinag, Austria’s national motorway operator. Work on both tubes, each 4.3km long, will start this month and be finished in June 2017. The €34 million contract includes upgrading the road and tunnel surfaces as well as reinstalling all electrical and mechanical equipment. Thomas Birtel, chief executive of the Strabag Group, said in a statement that the contract will be covered by the group’s construction, engineering and c
  • Lueg Bridge work sparks congestion fears
    June 23, 2022
    Lueg Bridge, along Austria’s section of the Brenner Pass route, is slated for major rehabilitation work as part of upgrades to the tolled motorway.
  • TBM for Gotthard Tunnel drive
    August 9, 2024
    A new TBM will be used to drive the new Gotthard Tunnel tube.
  • Opening set for Bikos Tunnel section of R4
    June 5, 2023
    Opening of the first stage of Slovakia’s R4 Presov-Northern Bypass expressway, including the 1.1km-long twin-tube Bikos Tunnel, is set for this summer.