Breakthrough for Slovenian Karavanke Tunnel

The existing tunnel Karavanke Tunnel tube between Austria and Slovenia opened in 1991.
By David Arminas April 2, 2024 Read time: 2 mins
The Slovenian stretch of the second tube alongside the original tube for the Karavanke Tunnel is around 3.5km, while Austria has had to excavate 4.5km (image courtesy Asfinag/DARS)

After three and a half years of excavation, Slovenia has broken through to the Austrian side of the second tube for the 7.9km-long Karavanke tunnel.

It was two years ago that boring on the Austrian side reached the border point with Slovenia, according to Asfinag, Austria’s government-owned company that manages the country’s highways.

The Slovenian stretch of the second tube is around 3.5km while Austria has had to excavate 4.5km.

Turkish tunnelling contractor Cengiz has done the excavation work on the Slovenian side under a contract signed with the Slovenian state-owned motorway company DARS for the €120 million project at the end of January 2020. The European Investment Bank, EIB, soon after lent the project €90 million.

This new tube, alongside the existing one that opened in 1991, should double the capacity of road transport between Villach, Austria, and Jesenice in Slovenia.

Construction of the second tube between the two countries started in August 2020. Delays on the Slovenian side have been attributed to challenging geological conditions, according to DARS.

Slovenia’s infrastructure minister Alenka Bratušek said he anticipates the second tube to open to traffic in 2025. However, after the new tune opens, work will start on renovating the original tube that is expected to be finished in late 2028.

Construction of the original tunnel began in 1986 to connect the Austrian Karawanken Autobahn , the A11, from Villach with the A2 motorway leading to Kranj and Ljubljana in Slovenia. The opening led to fewer vehicles using the historic Loibl/Ljubelj and Wurzen/Korensko sedlo mountain passes.

Early on in the new project, ASFINAG selected to use BIM, Building Information Modeling, for all relevant structural data, compiling a 3D-model as the project progressed.

For more information on companies in this article

Related Content

  • Switzerland’s new tunnel bore being built
    April 19, 2018
    A major new road tunnel project is being constructed in Switzerland – Mike Woof writes Construction work is now underway in Switzerland for the new Belchen Tunnel bore, a project that has resulted from the country’s long-term infrastructure planning. The building of this latest tunnel is important for Switzerland economically as it will deliver an upgraded link for a major transport infrastructure connection. When it is complete, the tunnel will form part of the vital A2 route between Basel, in the north
  • Checking up on the Czech Republic's Via Salis
    May 20, 2022
    Construction of the Via Salis, the Czech Republic’s first public-private partnership for a road project, is on schedule, according to VINCI which is leading the construction and operating consortium.
  • Slovakia starts on Presov northern bypass
    August 15, 2019
    Work has started on the first stage of the 4.3km-long Presov northern bypass, part of the R4 speedway in eastern Slovakia.
  • Bechtel Enka opens first section of Pristina-Skopje motorway
    October 29, 2015
    The first part of the €600 million Arber Dzaferi motorway between Pristina, the capital of Kosovo and Skopje in Macedonia, has opened to traffic. US-Turkish consortium Bechtel Enka is contractor for the 60km road that will eventually link Pristina, capital of the former Serbian province Kosovo, and the city of Skopje, capital of Macedonia, a former Yugoslav republic. The road - numerically Route 6 – is Kosovo’s second motorway and is named after the prominent Albanian intellectual and politician from