Breakthrough near for Čebrať Tunnel

The 3.5km-long tunnel through Slovakia’s Čebrať Hills is part of the D1 Ružomberok bypass.
By David Arminas December 17, 2021 Read time: 2 mins
The Ružomberok bypass project including the Čebrať Tunnel is expected to be open by the end of 2023 (image courtesy Slovak National Road Company/NDS)

The last 150m of Slovakia’s Čebrať Tunnel should be completed by the end of this year.

The 3.5km-long tunnel through the Slovakia’s Čebrať  Hills is part of the D1 motorway Ružomberok bypass project between Hubova and Ivachnova. The national motorway company NDS also noted that work is continuing on the western portal of the tunnel.

The Ružomberok bypass project is expected to be completed by the end of 2023 and will cut the journey between the two towns by over 16 minutes. It was supposed to be completed in 2017.

However, the project, originally to be only 2km long, had to be redesigned to 3.5km due to a landslide around the western portal of the tunnel. As a result the cost of the project increased to over €290 million (US$335.2 million).

Construction works are being carried out by the Slovak-Czech consortium Vahostav-SK and OHL ZS.

For a video of work on the tunnel, click here.

Ružomberok, with a population of around 45,000 including its surrounding area, is in the Liptove region in northern Slovakia. It lies around 260km from the Slovakian capital Bratislava.

Earlier this year, Swedish contractor Skanska started on a €255 million deal for work on the 13.5km D1 highway stretch between Lietavská Lúčka and Dubná Skala. It includes construction of the Višňové Tunnel, the longest road tunnel in Slovakia and which will help reduce journey times in the area around Žilina.

For more information on companies in this article

Related Content

  • Colas-built bridge opens over River Ipoly
    August 9, 2023
    Colas divisions in Hungary and Slovakia cooperated on constructing a recently opened bridge between Ipolydamasd in Hungary and Helemba in Slovakia.
  • Slovakia, Salini Impreglio to part ways over D1-Višňové tunnel work
    March 11, 2019
    Slovakia and the Italian-Slovak consortium of Salini Impregilo and Dúha will reportedly end construction of a D1 highway stretch including the Višňové tunnel. The planned 7.5km twin-tube Višňové Tunnel is part of the 13.4km section of the D1 between Lietavská Lúčka and Dubná Skala in northern Slovakia. Work started on what will be Slovakia’s longest tunnel in in June 2015. It is also part of the Corridor 5 of the Trans-European Networks (TEN) which links Bratislava with Uzhhorod in Ukraine and is financed
  • EC approves Slovakian highway project
    March 23, 2015
    The EC has given its approval for funding to construct the section of the D1 highway that will connect Hubova with Ivachnova. The EC will provide €169.2 million for the project. In all the 15.3km section of the highway will cost €227.26 million to construct, with the remainder being provided by the state budget. The construction is being carried out by a consortium combining Czech company OHL ZS and Slovak firm Vahostav SK. The work is now underway and the highway is expected to be open to traffic by June 2
  • US$5 billion turnpike widening work spans Route 66
    April 25, 2024
    A bridge replacement over historic Route 66 forms part of Oklahoma’s US$5 billion turnpike widening.