Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • Alpha 330 drilling tool system from Sandvik
    January 6, 2017
    Sandvik Construction is launching its new Alpha 330 drilling tool system for drilling and tunnelling. It has been developed with special features that control power and ensure this power is transmitted into the rock as efficiently, accurately and economically as possible. The company says that in tests, in varying rock conditions, the new design has been proven to deliver a 30-80% increase in rod life; provide more accurate collaring and straighter blast-holes, thereby delivering greater advancement and imp
  • Alpha 330 drilling tool system from Sandvik
    February 13, 2013
    Sandvik Construction is launching its new Alpha 330 drilling tool system for drilling and tunnelling. It has been developed with special features that control power and ensure this power is transmitted into the rock as efficiently, accurately and economically as possible. The company says that in tests, in varying rock conditions, the new design has been proven to deliver a 30-80% increase in rod life; provide more accurate collaring and straighter blast-holes, thereby delivering greater advancement and imp
  • Tees Valley crossing project consultation nears an end
    May 9, 2019
    Public consultation is nearly closed for a possible new crossing across the River Tees in northern England that could cost upwards of €350 million. A €230-290 million Tees Viaduct Capacity Enhancement project is the preferred option against a €350 million Tees Viaduct option, according to the recently created Tees Valley Combined Authority, the local government. Capacity Enhancement project would see a two-lane bridge built parallel to the existing A19 viaduct to carry traffic travelling northbound an
  • ENKA wins award for work on Kosovo highway project
    May 13, 2013
    Turkish contractor ENKA and its joint venture partner Bechtel have won the Best Global Project Award from US magazine Engineering News Record (ENR) for the Kosovo Route 7 highway project. The privately owned firm ENKA and Bechtel won an award in ENR’s Global Best Competition 2013 for the Project of the Year in the category for Roads and Highways around the world. Projects in several categories competed in the awards on factors such as innovation and overcoming global challenges, implementation of safety pro