Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems. The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an ap
August 31, 2018 Read time: 3 mins
Testing, testing: Seattle Tunnel Partners making sure that equipment and signage operates effectively in the soon-to-open Alaskan Way Tunnel in Seattle (photo courtesy WSDoT)
Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.


The client, Washing State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by as early as late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an aging 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, %$Linker: 2 Internal <?xml version="1.0" encoding="utf-16"?><dictionary /> 2 33214 0 link-external key project report false /categories/road-highway-structures/features/bertha-ends-her-alaskan-way-voyage-in-seattle/ false false%>, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened likely this fall.


Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners - a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems

For more information about the Alaskan Way Viaduct Replacement Program, see the website:

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 link-external www.alaskanwayviaduct.org false http://www.alaskanwayviaduct.org/ false false%>

For more information on companies in this article

Related Content

  • myPERI online portal presented in detail for first time during bauma
    February 13, 2013
    myPERI online portal will be presented in detail at a major construction equipment industry trade show for the first time during bauma. It gives customers of the internationally-renowned German formwork solution company round-the-clock access to extensive technical information and specific project data for their PERI construction sites. Project-specific reports, which offer, principally, a detailed overview of material stocks and flows, are said to be particularly advantageous for construction work.
  • Mitas adds to earthmoving tyre range
    April 17, 2013
    Mitas has unveiled the newest addition to its family of ERL earthmoving tyres, the 20.5R25 ERL-50. The tyre will become available for sale worldwide by July. Mitas makes specific tyres for machines operating in demanding conditions, including gravel and rock quarries. The Mitas ERL series features 12 tyres of 28mm to 90mm tread depth, with the ERL-50 designed for rocky conditions.
  • Innovative pre-casting technology is available from PRENSOLAND
    January 6, 2017
    Spanish company PRENSOLAND seeks to push the boundaries of concrete pre-casting technology with its new machinery and equipment developments. Novel technologies are now being introduced what are said to be more versatile with regard to the size and shape of product as well as the manufacturing quality and mechanical properties.
  • Innovative pre-casting technology is available from PRENSOLAND
    March 27, 2013
    Spanish company PRENSOLAND seeks to push the boundaries of concrete pre-casting technology with its new machinery and equipment developments. Novel technologies are now being introduced what are said to be more versatile with regard to the size and shape of product as well as the manufacturing quality and mechanical properties.