Ringway nears the end of a 300km road marking project in Hertfordshire

Highways contractor Ringway is nearly finished refreshing more than 300km of road markings for Hertfordshire County Council, north of London, in the United Kingdom. Two road marking crews consisting of two operatives have been working since April and are due to finish this month. They have been working predominantly at night to minimise disruption to the travelling public. Work is prioritised based on national road hierarchy - A, B, C and unclassified roads, said Kevin Carrol, Ringway’s Hertfordshire div
December 11, 2015 Read time: 2 mins
Highways contractor 2393 Ringway is nearly finished refreshing more than 300km of road markings for Hertfordshire County Council, north of London, in the United Kingdom. Two road marking crews consisting of two operatives have been working since April and are due to finish this month. They have been working predominantly at night to minimise disruption to the travelling public.

Work is prioritised based on national road hierarchy - A, B, C and unclassified roads, said Kevin Carrol, Ringway’s Hertfordshire divisional manager. Ringway’s seven-year contract with Hertfordshire County Council, estimated at the time to be worth more than €44 million, went live in October 2012 and has a potential five-year extension. It covers all aspects of road and footway maintenance and improvement, street lighting and winter service.

Ringway is the local authority contract highways maintenance business of 3281 Eurovia UK, which is owned by 5177 Vinci. Eurovia’s other divisions include Eurovia Contracting and Eurovia Surfacing, Eurovia Airport Services, Eurosigns and Eurovia Roadstone, formerly Ringway Roadstone, the UK asphalt production arm of Eurovia. Another division, Eurovia Specialist Treatments, formerly Ringway Specialist Treatments, provides solutions for improving and renewing the surfaces of footways, roads, airfields and car parks.

For more information on companies in this article

Related Content

  • Implementation of road building projects in Russia’s Moscow may be significantly delayed
    May 15, 2014
    Implementation of some large-scale investment projects for road building in Russia’s capital Moscow may be significantly delayed A series of major documentation issues are the cause of the problem. These have delayed projects for up to nine tenders on the total sum of US$2.6 billion (95 billion rubles), with anomalies having been found by the Russian Federal Anti-Monopoly Service.
  • UK’s Sandwell Council awards signal maintenance contract to telent
    September 28, 2018
    UK technology and network services company telent has been awarded a four-year contract to provide traffic signal maintenance services to England’s Sandwell Council. The deal marks the third win for telent’s traffic business in 2018, following wins with Stoke-on-Trent City Council and Oxfordshire County Council, both also in England. The Sandwell deal – tendered - sees telent retain its decade-long contract. It covers 109 traffic signal junctions, 174 pedestrian crossings and eight journey-time monitoring
  • Royal Engineers complete paving course
    November 30, 2012
    Personnel from the Royal Engineers Corps have recently completed a paver course attachment with Eurovia Surfacing, the road and pavement surfacing specialist. The course saw the Corps learn how to design, build and maintain a military road network or airfield when deployed abroad. The students were given a full site safety induction on arrival and spent three days with the Eurovia Surfacing team as they looked to fulfil criteria towards achieving their Military Plant Foreman titles. “We are extremely gratef
  • LagoonHull still on the cards
    February 7, 2022
    A proposed major river development in Hull would include an immersed road tunnel to connect traffic arriving from Europe with the UK’s motorway network.