Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • Virginia Interstate highway upgrade project
    February 26, 2019
    A 15km stretch of Interstate 64 in the US state of Virginia will be upgraded, allowing it to handle more traffic.
  • TBMs cut routes through Wuxi
    May 29, 2013
    Often used in road construction in China, eight Herrenknecht tunnel boring machines (TBMs) have now excavated almost 16km of tunnel in 20 months. The machines mastered challenging tunnelling stretches with small overburdens, crossing beneath the emerging metropolis of Wuxi, eastern China, to excavate the first two metro lines in the 3,000-year-old town on Taihu Lake, near Shanghai. Lines 1 and 2, with a total length of 58.5km, are expected to start operation in 2014. A total of five metro lines are planned.
  • JMT and Parsons get a Nice Bridge contract in the US state of Maryland
    July 7, 2015
    In the US state of Maryland, a joint venture of Johnson, Mirmiran & Thompson (JMT) and Parsons Brinckerhoff has won a contract to replace the Harry W. Nice Memorial Bridge. The Maryland Transportation Authority awarded the $1 billion contract to replace the bridge, also known as the Potomac River Bridge and which was opened in 1940. The tolled 2.7km two-lane continuous truss bridge on US 301 spans the Potomac River between Newburg in Maryland and Dahlgren in the state of Virginia. Construction of the
  • Pöyry picks up tunnel project on Switzerland’s A2 motorway
    August 18, 2016
    The Swiss Federal Roads Office (FEDRO) has awarded Poyry detailed engineering planning work for the upgrading of operational and safety equipment in two major tunnels on the A2 motorway. The A2 forms the main north-south motorway in Switzerland, connecting Basel with Chiasso. The Schänzli and Hagnau tunnels have been in operation for four decades and are being completely refurbished. Pöyry has already been handling the structural measures and ventilation systems in the tunnels, said Marcel Winter,