Testing and striping underway for Seattle’s Alaskan Way tunnel

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
October 18, 2018 Read time: 3 mins
The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right (photo courtesy WSDoT)

Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, 914 Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways.

STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-week viaduct closure to realign the  SR 99 – called the Alaskan Way - into the new tunnel.

The project is called the Alaskan Way Viaduct Replacement Project after the section of SR 99 in Seattle called the Alaskan Way, a street running along the seafront. Part of the Alaskan Way is an ageing 3.2km viaduct – opened in 1953 - which is being replaced by the 2.7km tunnel almost directly beneath it. This will free up waterfront area for major inner city development (see World Highways, Key Project Report, November 2017).

The multi-layered tests of the tunnel's operational and safety systems includes pre-functional tests to ensure working of individual equipment such as a sprinkler head. Functional tests check that the equipment works together as a system, for example multiple sprinklers. Finally, integrated testing checks that multiple systems function together - heat detectors and video cameras operate with the fire suppression system.

Striping of the road decks inside the tunnel is also continuing. The stripes separate a deck into two 3.3m lanes, a 2.4m shoulder on the left side and a 0.6m buffer on the right.

Kiewit Infrastructure West has started traffic signal, striping and roadway signage work to switch traffic on Alaskan Way from under the viaduct to the west of it. The viaduct will eventually be demolished after the tunnel is opened, likely this fall.

Tunnel boring was completed last year by Bertha, the world’s largest diameter earth pressure balance tunnel boring machine at the time, with a cutterhead diameter of 17.5m. By the end of last year it had been dismantled, job completed.

Seattle Tunnel Partners is a joint venture of New York-based 4761 Dragados US (a subsidiary of Dragados, the construction division of ACS Group of Spain) and the general contractor Tutor Perini Corporation, based in California.

Apart from designing and building the tunnel - and owning Bertha - STP is responsible for building highway ramps and other connections at the north and south ends of the tunnel. STP is also constructing permanent buildings at the north and south portal to house lighting, ventilation and other essential tunnel systems.

For more information on companies in this article

Related Content

  • New Midtown Tunnel open in Virginia
    January 30, 2017
    A project to construct the second Midtown Tunnel link in the US state of Virginia alongside the original connection has taken an important step forward – Mike Woof writes Commuters in the US state of Virginia will be pleased that the new Midtown Tunnel is now open to traffic, as it will help to boost capacity and cut congestion on the busy US 58 route connecting Norfolk and Portsmouth. The 1.13km tunnel link has been built to link with the interchange at Brambleton Avenue and Hampton Boulevard in Norfolk
  • Nepal's new bridge link
    February 13, 2012
    Construction work is underway in Nepal on one of the biggest box-girder bridges ever built in the country. The bridge is located in Mid West Nepal and measures just over 1km long.
  • Austria's new tunnel meets safety regulations
    July 13, 2012
    New safety regulations and high traffic volumes require new tunnel construction all across Europe. Mike Woof reports Anew highway tunnel now being built in Austria will boost traffic volumes and safety standards on a key European route. The existing Pfänder Tunnel lies close to Austria's borders with Germany and Switzerland and carries a heavy traffic volume, so a new parallel tunnel is under construction to help spread this load, increasing capacity as well as safety. Stringent tunnel safety standards have
  • New tunnelling technology saves time
    February 15, 2012
    New tunnelling technology from BASF has helped cut construction time on a major tunnel project in Australia. The system has been used to speed waterproofing, an important point as the link runs underneath one of Australia's major rivers. The spray-applied polymer membrane provided by a BASF sprayed concrete machine saved time and effort on the construction of the Clem Jones 7 Tunnel (Clem 7) in Brisbane, Australia. The 4.8km tunnel was completed seven months ahead of schedule and at its lowest point Clem 7